30 Jun 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100027574

Delivery and registration

When is the project declared for completion?

FORTUNE PRIDE is registered with MahaRERA as P52100027574 and the promoter has declared completion for 30 Jun 2026.

30 Jun 2026

declared completion

3months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100027574
Registered on16 Dec 2020
Promoter-declared completion30 Jun 2026
Current statusCertificate Signed
Against todayabout 3 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for FORTUNE PRIDE record 23 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Fortune Pride is the promoter of record on 122 projects registered with MahaRERA, 15 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

122projects

registered with MahaRERA

15flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for FORTUNE PRIDE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
A BUILDING1G+1731 Dec 2025
B BUILDING1G+1731 Dec 2025
C BUILDING1G+1731 Dec 2025
D BUILDING1G+631 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at YEWLEWADI, S NO 10/2/1, Pune City, Pune, 411048. Per the filed land record, the plot is bounded to the north by SURVEY NO 9, to the south by SURVEY NO 10, to the east by PROJECT OF ALCON GROUP and to the west by SASWAD KONDHAWA ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kondhwa Khurd

Krushna Chayya
possession by Sep 2026 · Shree Mahalaxmi Builder AND Developars
Majestic Pride
possession by Oct 2026 · Anwar Mahmoo Shaikh
Krishna Kapital
possession by Dec 2026 · Ostwal Realty
Akshardham Phase 2
possession by Dec 2026 · Shreyan Ventures
Clover Highlands
possession by Dec 2026 · Clover Developers Pvt Ltd
Hagawane Landmark
Not filing quarterly progress reports · possession by Dec 2026 · Santosh Subhash Hagawane

Major developers building in Kondhwa Khurd

Other RERA-registered projects in Pune

Fortune Pride
possession by Jun 2028 · Sachin Vijaykumar Jadhav
Fortune Prima
declared completion Sep 2026 · Satish Shivlal Kokate
Fortune Prospero
declared completion Dec 2025 · Fortune Homes
Fortune Revanta
possession by Dec 2029 · Not Available
Fortune Sakar
possession by Mar 2029 · M/s. Fortune Developers
Fortune Vedanta
declared completion Apr 2025 · Fortune Associates

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 15 Sep 2026