MahaRERA Property Intelligence · Pune
P52100008069 · promoter Pravin Uttam Bhintade
Free before you decide: the 14 things to get in writing before you book
Every item comes from a real RERA filing. Send it to the family group before anyone pays a token.
Send the checklist to the family group Read it here →Delivery and registration
GANESH NAKSHATRAM is registered with MahaRERA as P52100008069 and the promoter has declared completion for 30 Oct 2020.
30 Oct 2020
declared completion
71months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100008069 |
| Registered on | 18 Aug 2017 |
| Promoter-declared completion | 30 Oct 2020 |
| Current status | Certificate Signed |
| Against today | about 71 months past the declared date |
Approvals and compliance
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GANESH NAKSHATRAM record 14 quarterly progress reports since registration.
14quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
Promoter record
Pravin Uttam Bhintade is the promoter of record on 7 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
7projects
registered with MahaRERA
1flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
No registered sale-agreement price is recorded for GANESH NAKSHATRAM in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| GANESH NAKSHTRAM | 1 | G+12 | 31 Mar 2019 |
No buyer complaints were on this project's MahaRERA record at the time of reading.
The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 30 Apr 2020 | The project 'GANESH NAKSHATRAM' could not obtain all nescessary NOC's due to change of local competent authority i.e from PMRDA to PMC Pune causing delay in obtaining completion |
| 30 Apr 2020 | 30 Apr 2020 | 1) I have applied for extension of project in which I have declared the date of completion of the building as 31.03.2019. 3) But due to change in local competent authority i.e. P |
Located at Haveli, Pune, 411041. Per the filed land record, the plot is bounded to the north by PARTY BY 30 MTR PROPOSED DP ROAD, to the south by SR NO 126 VILLAGE OF KIRKATWADI, to the east by SR NO 127 and to the west by VILLAGE KIRKATWADI. These are the boundaries as recorded in the filed land record.
The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Pune Junction / city centre | 12 km |
| Baner–Balewadi belt | 13 km |
| Magarpatta / Hadapsar IT | 16 km |
| Hinjewadi Rajiv Gandhi IT Park | 17 km |
| Kharadi / EON IT Park | 19 km |
| Pune Int'l Airport (Lohegaon) | 20 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 What I’d do as a buyer here · Drawings Report
The report opens with what this project really is — read from its approved drawings — then the specific calls: the cheapest good way to buy here, the home to say no to, what you can stop worrying about, and what to get in writing before you sign anything.
🔒 Which home to ask for · Drawings Report
The home-level read: which ones to prefer and which to avoid, what the drawings put around each, and the things on this site nobody at the sales desk will tell you about.
The approved drawings
A thin filing
The crawled listing for GANESH NAKSHATRAM shows only one approved drawing — not enough drawn material for a useful unit-level read, and we would rather tell you that than sell you a thin report. The register record above is what this filing carries.
Want this project read from its filed drawings?
The completion date has been revised 2 times on the register. We read every approved drawing on GANESH NAKSHATRAM’s file and tell you which homes we would ask for, what sits around them, and what to get in writing before you pay the token.
This page is the free MahaRERA filing summary. For GANESH NAKSHATRAM: what the approved drawings and filed papers say about the homes, the parking, the approvals — and what to get in writing before you sign. That is the Drawings Report.
Drawings Report · ₹4,999
This project has a thin public drawing file — the crawled listing shows one approved drawing or none. We check the current filing first, and only take payment if there is enough to read.
Paying from outside India? Pay $59 (Drawings Report) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 10 Sep 2026