Pune/Project record

MahaRERA · the public record

GOKUL VILLA

KOREGAON MUL · GOKUL VILLA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100046025

Delivery and registration

When is the project declared for completion?

GOKUL VILLA is registered with MahaRERA as P52100046025 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100046025
Registered on15 Jun 2022
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GOKUL VILLA record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 11 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Gokul Villa is the promoter of record on 31 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

31projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In GOKUL VILLA, 0 of 125 plots filed with MahaRERA are recorded as sold or booked, about 0%, and 125 remain available.

0%sold

0 of 125 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GOKUL VILLA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KOREGAON MUL, KOREGAON MUL, Pune City, Pune, 412202. Per the filed land record, the plot is bounded to the north by BY GAT NO 410 AND PROPERTY OF RAILWAY, to the south by BY PUNE SOLAPUR HIGHWAY, to the east by REMAINING LAND OF GAT NO 410 1 and to the west by BY NAYGAON SHIV ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Uruli Kanchan

Siddhi Sankul
possession by Sep 2026 · Jitendra Constructions AOP
Elite II
Not filing quarterly progress reports · possession by Dec 2026 · Landmark Development Corporation PVT LTD
Srinivas Empire
Not filing quarterly progress reports · possession by Mar 2027 · Srinivas And Associates
Sahyadri
possession by Aug 2027 · Sahyadri Builders And Developers
Green Fantasy Phase-I
possession by Dec 2027 · Shree Mangalmurti Associates Phase-I
Sunrise Villa
possession by Dec 2027 · White House Construction

Other RERA-registered projects in Pune

Gokuldhaam
possession by Dec 2028 · Setu Developers
Gokuldham
declared completion Dec 2022 · R K Associates
Gokuldham 4th Avenues
possession by Dec 2027 · Eight Sqft Realtech
Gokuldham Residency
possession by Dec 2027 · K Construction
Gokuldham Society
declared completion Mar 2019 · Jadhav AND Gandhi Associates
Golan Heights
possession by Jun 2027 · Divyayasha Builders Promoters AND Develo

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 15 Sep 2026