JAYANT HEIGHTS

KASBA PETH · YUVRAJ NIVRUTTI RUKE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jan 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jan 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100026275

Delivery and registration

When is the project declared for completion?

JAYANT HEIGHTS is registered with MahaRERA as P52100026275 and the promoter has declared completion for 31 Jan 2024.

31 Jan 2024

declared completion

32months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100026275
Registered on04 Sep 2020
Promoter-declared completion31 Jan 2024
Current statusCertificate Signed
Against todayabout 32 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for JAYANT HEIGHTS record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Yuvraj Nivrutti Ruke is the promoter of record on 22 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

22projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for JAYANT HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
JAYANT HEIGHTS1G+831 Jul 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KASBA PETH, KASBA PETH, Pune City, Pune, 411011. Per the filed land record, the plot is bounded to the north by 785 AND 788 KASBA PETH, to the south by 545 KASBA PETH, to the east by 795 KASBA PETH and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kasba Peth

Anandi Madhav Smruti
possession by Dec 2026 · Sehgnor Developers LLP
72 Residence
Not filing quarterly progress reports · possession by Dec 2026 · Sunil Bapusaheb Shinde
Antriksh Towers
possession by Dec 2026 · AUM Cityscapes LLP
Antriksh Towers 22-32
possession by Dec 2026 · AUM Cityscapes LLP
Bhoishwaram
possession by Dec 2026 · M/s Aparna Builders
Dhanalaxmi Sanskriti
possession by Dec 2026 · Shubh Realty

Other RERA-registered projects in Pune

Jayant Residency
declared completion Jun 2021 · Indrasen Jayant Kakade
Jayhind Ample
possession by Apr 2027 · Jayhind Group Builders
Jayhind Homes
declared completion Dec 2021 · Sagar Jaysing Erande
Jayka Synergy Tower
possession by Dec 2028 · Baner Pashan 5 Realty LLP
Jaylaxmi Complex
declared completion May 2022 · M/S Mahalaxmi Builders & Developers
Jaymala Business Court
declared completion Apr 2019 · Satyam Constructions

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.