Pune/Project record

MahaRERA · the public record

OXY ETERNO

DHANORI · KEYSTONE ETERNO LLP

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

1units filed as unsoldInventory · 19 July 2026
30 Jun 2025declared completionMahaRERA registration · read 19 Jul 2026
99registered unitsMahaRERA registration · read 19 Jul 2026

From another project · Life Republic Atmos Phase II

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Life Republic Atmos Phase II Project Review · first page
First page of the complete sample.

Free project details

Registration read 19 Jul 2026

RERA details for OXY ETERNO

MahaRERA · P52100027735

Delivery and registration

When is the project declared for completion?

OXY ETERNO is registered with MahaRERA as P52100027735 and the promoter has declared completion for 30 Jun 2025.

30 Jun 2025

declared completion

16months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP52100027735
Registered on03 Jan 2021
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 16 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for OXY ETERNO record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 19 Jul 2026

View the free 14-item checklist →

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Sales

How many are filed as sold or booked?

In OXY ETERNO, 98 of 99 homes filed with MahaRERA are recorded as sold or booked, about 99%, and 1 are filed as unsold.

99%sold or booked

98 of 99 homes

₹54.13 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹51.92 Cr (about 96%) is recorded as collected and ₹2.40 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 19 Jul 2026

Filed agreement values: across 98 sold or booked entries with usable filed values and areas, the effective carpet rate is ₹8,897/sqft, with eight in ten falling between ₹7,272 and ₹9,349 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the unit.

FloorUnitCarpetGovt reckoner value
Floor 1A-101779 sqft (72.4 sqm)₹53.91 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 19 July 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific home. On this project 98 homes carry one, and 1 of the 99 are recorded unsold.

Here is one home filed as unsold, beside the amounts filed for comparable homes:

HomeCarpetFiled comparisonBased on
A-101779 sqftRs 73.56 lakh typical, over Rs 52.00 lakh to Rs 94.59 lakh8 filed · number pattern + area (within 2%), same building

A filed consideration is the amount the promoter reported for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In OXY ETERNO, every one of the 1 unsold homes has filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.

See all 98 filed sold/booked entries — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10 and 99 homes are registered across the project.

BuildingWingsFloorsUnitsDeclared completion
A WING1G+1099-

Unit mix on the filing: 99 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2024Reason for delay is due to material cost increases, 2 Flats booking issue & Completion (NOC) issue.
31 Dec 202430 Jun 2025Reason for delay is due to material cost increases, 1 Flats booking issue & Completion (MPCB CONSENT TO OPERATE & NALA NOC’S) issue.

Location, Land & Connectivity

Located at DHANORI, BHARAT DHABA CHOWK, BEHIND SAI DHAM SOCIETY, Haveli, Pune, 411015. Per the filed land record, the plot is bounded to the north by BY SAI DHAM SOCIETY, to the south by BY ROAD, to the east by S NO 22 PART and to the west by BY ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 8293 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park8293 km
Baner–Balewadi belt8297 km
Pune Junction / city centre8307 km
Magarpatta / Hadapsar IT8312 km
Pune Int'l Airport (Lohegaon)8312 km
Kharadi / EON IT Park8314 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dhanori

Galaxy Co-Operative Housing Society Ltd
declared completion Oct 2026 · Yash Developers
Austin
declared completion Dec 2026 · Krishna Venture Skyscraper LLP
Maitri Chandrika
declared completion Dec 2026 · S K Promoters
Mauli Prastha
declared completion Dec 2026 · Yashashree Promoters AND Builders
Palladium Homes-II, B Building
declared completion Dec 2026 · Raojee Constructions
Shubhankar Durvaa Phase II A
declared completion Dec 2026 · Atul Dnyaneshwar Bahirat
More builders in Dhanori

Major developers building in Dhanori

More projects in Pune

Other RERA-registered projects in Pune

OXY Flora
declared completion Dec 2024 · Yogesh Developers
OXY Flora Phase 2
declared completion Dec 2022 · OXY Flora Phase 2
OXY Flora Phase 3
declared completion Dec 2026 · Yogesh Developers
OXY Galaxy
declared completion Jun 2018 · Venkatesh Estate
Oxy Gold D
declared completion Aug 2022 · M M Developers
Oxy Gold E Building
declared completion Dec 2026 · M M Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.