Developer RERA record

Goel Ganga

Goel Ganga has 18 RERA-registered projects: 9 projects under construction; 9 projects past their declared completion date. All figures are the developer's own regulator filings.

On the register
Delivery signal
9
Under construction
9
Past declared date

Under construction

Under construction — 9 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
Ganga Altus Wing FPunepossession by Jun 2028
Ganga Arcadia A BuildingPunepossession by Mar 2027
Ganga Utopia CommercialPunepossession by Dec 2026
Ganga Utopia E BuildingPunepossession by Dec 2026
GG Town Wagholi Phase B Building 8 AND 9Punepossession by Jun 2028
GG Town Wagholi PunePunepossession by Jun 2027
ONE Boat ClubPunepossession by Dec 2030
Pune Baner Project-Tower 3Punepossession by Jun 2030
Pune Baner Project-Tower 4 And 5Punepossession by Jun 2030
Considering a specific Goel Ganga project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (9)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
Ganga AashrayPune2024-12
Ganga Aria APune2023-12
Ganga Aria B1 B2Pune2020-12
Ganga Millennia Undri Building J AND KPune2025-06
Ganga Serio E F BuildingPune2024-12
Ganga Serio G BuildingPune2025-12
Kamal C1 C2Pune2019-12
Shriniwas Liviano Phase IPune2021-03
Wagholi Plotted DevelopmentPune2024-06

Request the report on Goel Ganga

We analyse Goel Ganga in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Figures are Goel Ganga's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.