Pune/Project record

MahaRERA · the public record

SHRINIWAS LIVIANO PHASE I

Kharadi · GOEL GANGA LANDMARKS LLP

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Mar 2021declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for SHRINIWAS LIVIANO PHASE I

MahaRERA · P52100018256

Delivery and registration

When is the project declared for completion?

SHRINIWAS LIVIANO PHASE I is registered with MahaRERA as P52100018256 and the promoter has declared completion for 30 Mar 2021.

30 Mar 2021

declared completion

67months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP52100018256
Registered on17 Oct 2018
Promoter-declared completion30 Mar 2021
Current statusCertificate Signed
Against todayabout 67 months past the declared date

Promoter record

What else is this promoter on record for?

GOEL GANGA LANDMARKS LLP is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 19 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHRINIWAS LIVIANO PHASE I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
A WING1G+1631 Mar 2019
B WING1G+1531 Mar 2019
C WING1G+1531 Mar 2019
D WING1G+1531 Mar 2019

Legal and disputes

What disputes are disclosed?

13 complaints are on the MahaRERA record for SHRINIWAS LIVIANO PHASE I, with orders passed in 13 of them.

13complaints

13with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 19 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000006485122/11/2020Mukesh Gupta vs Sudhir Darodeorder passed
CC00500000013715029/05/2022Mukesh Gupta vs Darode Jog Realities private limitedorder passed
CC00500000002248721/01/2019Swapnil Santosh Tholiya vs Darode Jog Realities Private Limited Sudhir Chandrakant Darode and Anand Dhaundiraj Jogorder passed
CC00500000002215318/10/2018Vishal Ravindra Madan vs Darode Jog Realities Pvt Ltdorder passed
CC00500000002221813/01/2019Abhishek Laddha vs Sudhir Darodeorder passed
CC00500000002223813/11/2018Mr. Asif Akbar Parpia vs Darode Jog Realities Private Limitedorder passed
CC00500000002237223/12/2018Pradeep Surendra Saxena vs Darodejog realities pvt ltdorder passed
CC00500000002252310/02/2019Sonal Mehta vs Darode Jog Realities Pvt Ltdorder passed
CC00500000002261304/02/2019SURESH G PHADTARE vs SUDHIR CHANDRAKANT DARODE, 2..ANAND DHUNDIRAJ JOG , DIRECTOERS , DARODE JOG REALITIES PVT LTD.order passed
CC00500000002260112/02/2019ZARNA S DOSHI, SUKETU C DOSHI vs DARODE JOG REALITIES PVT LTDorder passed
CC00500000002263006/02/2019ATUL SADRANI vs Darode Jog Realties Pvt Ltdorder passed
CC00500000002342215/09/2019SHRIKANT SUREKA vs SUDHIR CHANDRAKANT DARODEorder passed
CC1250146901/05/2025PINAKIN GANGJ SATRA vs GOEL GANGA LANDMARKS LLPorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Mar 2021Reason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. War, Civil Commotion or Act of God. b. Any noti

Location, Land & Connectivity

Located at Kharadi, Mouje Kharadi , Pune City, Pune, 411014. Per the filed land record, the plot is bounded to the north by S NO 17 and S No 22, to the south by S NO 18 and S No 19, to the east by Liviano Phase II and to the west by S N0 21 and S No 22. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kharadi

Ganga Platinum A
declared completion Oct 2026 · Shree Balaji Associates Pune LLP
Percept Bounty 3
declared completion Dec 2026 · Prime Estate
Grant Bay
declared completion Dec 2026 · Gagan Landmarks LLP
Bramhacorp Smart
declared completion Dec 2026 · Bramhacorp Limited
Orville Business Port
declared completion Dec 2026 · Siddhesh Properties
Panchshil Avenue
declared completion Dec 2026 · New Level Business LLP
More builders in Kharadi

Major developers building in Kharadi

More projects in Pune

Other RERA-registered projects in Pune

Shriniwas Serene County Phase III
declared completion Dec 2023 · Darode JOG AND Associates
Shriniwas Serene County Wing J & K
declared completion Oct 2028 · Vidyashree Developers Unit-1 LLP
Shriniwas Sinhgad County
declared completion Jul 2022 · Darode JOG Kulkarni Venture
Shriniwas Westside County Phase II
declared completion Dec 2023 · Darode JOG Builders PVT LTD
Shripad
declared completion Mar 2029 · Kale B J Builders AND Developers
Shripal Park
declared completion Mar 2027 · Shripal Landmarks AOP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.