Pune/Project record

MahaRERA · the public record

VAIBHAV POPATLAL MUTTHA

AUTI MALA · VAIBHAV POPATLAL MUTTHA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100033343

Delivery and registration

When is the project declared for completion?

VAIBHAV POPATLAL MUTTHA is registered with MahaRERA as P52100033343 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100033343
Registered on16 Feb 2022
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VAIBHAV POPATLAL MUTTHA record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vaibhav Popatlal Muttha is the promoter of record on 11 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

11projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In VAIBHAV POPATLAL MUTTHA, 0 of 22 plots filed with MahaRERA are recorded as sold or booked, about 0%, and 22 remain available.

0%sold

0 of 22 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VAIBHAV POPATLAL MUTTHA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at AUTI MALA, OZAR ROAD, Junnar, Pune, 410504. Per the filed land record, the plot is bounded to the north by LAND OF YASHWANT AUTI, to the south by LAND OF GAJANAN AUTI AND OTHERS, to the east by LAND OF ANANT KULKARNI and to the west by S NO 143-7 NARAYANGAON. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~65 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)62 km
Kharadi / EON IT Park65 km
Hinjewadi Rajiv Gandhi IT Park65 km
Baner–Balewadi belt67 km
Pune Junction / city centre68 km
Magarpatta / Hadapsar IT69 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Narayangaon

Crystal Tower
possession by Dec 2026 · Jadhav Civil Project
Divyata Park
possession by Dec 2026 · Shantaram J Gadhve
Vizion Galaxy D
possession by Dec 2026 · Vizion Construction
Landmark Paradise
possession by Jul 2027 · Landmark Promoters & Builders
Prime Vastu
possession by Jul 2027 · Prime Construction
Gaurinandan Heights
possession by Dec 2027 · Trident Civil Projects

Other RERA-registered projects in Pune

Vaibhavi Society
declared completion Jan 2024 · K J Realtors
Vaibhavshree AND Indira Priyadarshani
possession by Sep 2026 · Pride Properties & Infrastructure
Vaidehi Riviera Wing B
declared completion Dec 2024 · Desai And Gaikwad
Vaishnav Classic
declared completion Dec 2017 · Shree Datta Developers
Vaishnav Gaatha
possession by Dec 2026 · Kalbhor Realtors And Services LLP
Vaishnav Residency
declared completion Dec 2018 · Vaishnav Residency

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 15 Sep 2026