Vajrakkaya

Kondhwa Budruk · Vajrakkaya Infra Ventures LLP

Project X-Ray · for this project

Before you book, see what you’re really buying.

The layout. The real costs. The commitments. We read the plans and filings together, so you can decide with a clearer picture.

Six checks for your project.

  1. The Family Fit Scan

    The quoted area does not tell you how the space can be used. We check the layout, access and permitted use.

  2. The Premium Lens

    Two similar-sized units can offer different usable space and access. We compare what the plans show before you pay more.

  3. The Unwritten Bill

    The unit price may leave out fit-out, services and shared charges. We flag the commitments in the available documents.

  4. The Neighbour Math

    Shared access and facilities affect how you use the property. We read the plans and the stated rights together.

  5. The Progress Pulse

    An overall completion figure can hide unfinished services. We read the detailed progress filings and their dates.

  6. The Lawyer’s Shortlist

    A small token can come with a much larger cancellation charge. We flag that, the seller’s authority and documents your lawyer should check.

See the report before you buy

See the findings, not just a list of checks.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project X-Ray sample ↗
31 Dec 2021declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Vajrakkaya

MahaRERA · P52100016558

Delivery and registration

When is the project declared for completion?

Vajrakkaya is registered with MahaRERA as P52100016558 and the promoter has declared completion for 31 Dec 2021.

31 Dec 2021

declared completion

59months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100016558
Registered on23 May 2018
Promoter-declared completion31 Dec 2021
Current statusCertificate Signed
Against todayabout 59 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Vajrakkaya record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Vajrakkaya in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
Vajrakkaya1G+231 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020The date of completion was 31/12/2019. But as per recent notification, 11 villages under PMRDA jurisdiction have been included in Pune Municipal Corporation limits which includes t
30 Dec 202031 Dec 2021Due to Covid - 19 and subsequent lockdown restrictions, the project is lagging behind. We have taken the allottees into confidence, taken their consent for extension of project to

Location, Land & Connectivity

Located at Kondhwa Budruk, Khadi Machine Chowk, Pune City, Pune, 411048. Per the filed land record, the plot is bounded to the north by S No 24 Part, to the south by 24 Mtr Wide Road, to the east by 9 Mtr Wide Road and to the west by S No 25. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kondhwa Bk

Krishna Kapital
declared completion Dec 2026 · Ostwal Realty
Akshardham Phase 2
declared completion Dec 2026 · Shreyan Ventures
Clover Highlands
declared completion Dec 2026 · Clover Developers Pvt Ltd
Hagawane Landmark
Not filing quarterly progress reports · declared completion Dec 2026 · Santosh Subhash Hagawane
Millennium Park
declared completion Dec 2026 · Xrbia Epoch Creations LLP
Sadguru Residency
declared completion Dec 2026 · MAA Pranaam Buildcon Private Limited
More builders in Kondhwa Bk

Major developers building in Kondhwa Bk

More projects in Pune

Other RERA-registered projects in Pune

Valame Enterprises Swami Samarth Nagar
declared completion Jun 2023 · Ashwini Prakash Valame
Valay
declared completion Jan 2020 · Suraj Raman Bhujbal
Valeentina Tower
declared completion Dec 2030 · Velentina 7 Buildcon LLP
Valenciya
declared completion Jun 2026 · M/s. Flynirvanna Builder LLP
Vallabh Co-Op Housing Society
declared completion Sep 2026 · Srkd Landmark LLP
Vallabh Heights
declared completion Sep 2026 · G R Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 11 Sep 2026. Document and inventory dates are shown in their sections.