Pune/Project record

MahaRERA · the public record

VENKETESHWARA GRUH NIRMAN

Pune · VENKETESHWARA GRUH NIRMAN

Project X-Ray · for this project

Before you book, see what you’re really buying.

The layout. The real costs. The commitments. We read the plans and filings together, so you can decide with a clearer picture.

Six checks for your project.

  1. The Family Fit Scan

    The quoted area does not tell you how the space can be used. We check the layout, access and permitted use.

  2. The Premium Lens

    Two similar-sized units can offer different usable space and access. We compare what the plans show before you pay more.

  3. The Unwritten Bill

    The unit price may leave out fit-out, services and shared charges. We flag the commitments in the available documents.

  4. The Neighbour Math

    Shared access and facilities affect how you use the property. We read the plans and the stated rights together.

  5. The Progress Pulse

    An overall completion figure can hide unfinished services. We read the detailed progress filings and their dates.

  6. The Lawyer’s Shortlist

    A small token can come with a much larger cancellation charge. We flag that, the seller’s authority and documents your lawyer should check.

See the report before you buy

See the findings, not just a list of checks.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project X-Ray sample ↗
31 Mar 2026declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for VENKETESHWARA GRUH NIRMAN

MahaRERA · P52100011099

Delivery and registration

When is the project declared for completion?

VENKETESHWARA GRUH NIRMAN is registered with MahaRERA as P52100011099 and the promoter has declared completion for 31 Mar 2026.

31 Mar 2026

declared completion

8months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100011099
Registered on31 Aug 2017
Promoter-declared completion31 Mar 2026
Current statusCertificate Signed
Against todayabout 8 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VENKETESHWARA GRUH NIRMAN record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2026-03-31).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VENKETESHWARA GRUH NIRMAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
PHASE 11G+1731 Mar 2019
PHASE 21G+1731 Mar 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2023Non receipt of occupation certificate.
31 Mar 202331 Mar 2026OCCUPATION CERTIFICATE NOT RECEIVED FROM PUNE MUNCIPAL CORPORATION

Location, Land & Connectivity

Located at Solapur, Pune City, Pune, 411029. Per the filed land record, the plot is bounded to the north by SURVEY NO 18 PART, to the south by SUVEY NO 19, to the east by HINGNE GAON and to the west by SURVEY NO 14. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 8 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Baner–Balewadi belt8 km
Pune Junction / city centre10 km
Hinjewadi Rajiv Gandhi IT Park13 km
Magarpatta / Hadapsar IT14 km
Kharadi / EON IT Park17 km
Pune Int'l Airport (Lohegaon)17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dahanukar Colony

Akshay Apartment
declared completion Jan 2028 · Aakar Constructions
Omkar CO-OP Housing Society
declared completion Apr 2028 · WNS Avishkar Developers
Ambar Parkview
declared completion Dec 2028 · Happy Nest Ventures
Devki Co-Operative Housing Society Limited
declared completion Jun 2026 · Shreesha Landmark
Anjalikunj
declared completion Mar 2026 · Ravetkar Realties
Shree Chinar Cooperative Society Limited
declared completion Mar 2026 · Saachee Infra
More projects in Pune

Other RERA-registered projects in Pune

Ventila Park
declared completion Nov 2025 · Krushnarang Builders
Venture City B AND C Wing
declared completion Jun 2026 · Venture Group
Venu Tower
declared completion Mar 2026 · Vighnaharta Developers
Venus Enclave
declared completion Dec 2025 · K P Abdul Rehman Ramees
Verdant 84
declared completion Dec 2025 · Verdant Realty
Veridian Park
declared completion Dec 2028 · Platinum Builders

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 30 Oct 2026. Document and inventory dates are shown in their sections.