Bangalore/Project record

K-RERA · the public record

BMK SKY VILLA

· Land Trades Builders and Developers

Project Review · example purchase

Spending a few crores on a villa? ₹4,999 to check what you’re buying.

Check what the plans put beside your villa, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best villas.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
60%construction reportedQ1 2026 filing
11units not bookedof 23 · Q1 2026 filing
23registered unitsK-RERA registration · read 16 Jul 2026

Free project details

Registration read 16 Jul 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 16 Jul 2026

Registered units and project size

Residential
23

Filed categories, unchanged · K-RERA registration · read 16 Jul 2026

The whole registration

0.5registered acres

47.4registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for BMK SKY VILLA

K-RERA · PRM/KA/RERA/1257/334/PR/041223/006450

Project facts and comparisons

On the register

Land area1,962 sq m (0.5 acres)
Homes registered23
Tower/wing entries1
Unit mix23 × Residential

In context

Density47.4 homes per acre
Density in context16th percentile of 4913 projects in this register (median 82)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units23Total inventory registered with K-RERA.
Official carpet area7,846 sqmTotal carpet area reported for the project.
Official built-up area13,876 sqmUseful scale context when comparing density and project cost.
Registered land area1,962 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI4.61Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)51Separate filed counts; these categories may overlap and are not added together.
Covered-parking field43Separate filed counts; these categories may overlap and are not added together.
Open-parking field8Separate filed counts; these categories may overlap and are not added together.
Garage field51Separate filed counts; these categories may overlap and are not added together.
Approved plan numberE8/BA 38/2023-24Use this to match the sanctioned drawing set shown by the builder.
Plan approval date17-10-2023
Project start date01-01-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Residential23100%6,263 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
BMK SKY VILLA24235194.48 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 23 official flat/unit rows, matching the 23 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
4 BHK23272.3 sqm4.3 sqm46

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
BMK SKY VILLA23272.3 sqm4.3 sqm46
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
201BMK SKY VILLA24 BHK272.3 sqm4.3 sqm2
301BMK SKY VILLA34 BHK272.3 sqm4.3 sqm2
401BMK SKY VILLA44 BHK272.3 sqm4.3 sqm2
501BMK SKY VILLA54 BHK272.3 sqm4.3 sqm2
601BMK SKY VILLA64 BHK272.3 sqm4.3 sqm2
701BMK SKY VILLA74 BHK272.3 sqm4.3 sqm2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

12 of 48 compliance document slots are filed as Not Applicable; the remaining 36 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

See the filed approval statuses and linked documents →

Statutory approval status

RERA filing

6 of 6 applicable approvals are marked Approved in the filing. Check the linked documents for their scope and validity.

4 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved02-11-2023Water permission letter .jpeg
KSPCB- PCB (10 Acres to 125 Acres)Approved10-03-2023KSPCB CFE BMK.pdf
KPTCL- BESCOMApproved08-11-2023Electricity board NOC.pdf
Fire and SafetyApproved16-10-2023Fire NOC BMK.pdf
Airport Authority of IndiaApproved12-06-2023Airport NOC BMK Sky Villa.pdf
BSNL/Telecommunication DepartmentApproved01-02-2023BSNL NOC BMK .pdf

Project team & certifications

RERA filing

K-RERA names 6 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantLaxmisha Rao K2431622012Udupi, Karnataka - 576101
EngineerShantilal Hastimal JainSTR/J/211984Mumbai City, Maharashtra - 400013
EngineerGokulrajMNG/BL/10156/20-212003Dakshina Kannada, Karnataka - 575003
ArchitectSaurabh ChatterjeeCOA/1994/171502004Mumbai City, Maharashtra - 400013
ArchitectGokulrajMNG/BL/10156/20-212003Dakshina Kannada, Karnataka - 575003
ContractorMfar Construction Pvt Ltd-1990Dakshina Kannada, Karnataka - 575001

Builder track record

RERA filing

Land Trades has 18 other K-RERA-registered projects in our records (average reported construction progress 51%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹4.62 Cr collected from buyers, ₹4.61 Cr withdrawn from the project's escrow account.

Construction progress33% → 60% (+27 pts)
Units sold/booked as registered12/23 (52%)
Buyer collections in available QPRs₹12.85 Cr
Escrow withdrawals in available QPRs₹9.67 Cr (0.75x collections)
  • Construction progress moved from 33% to 60% across the filed QPR window.
  • The builder has drawn 0.75x of buyer collections from escrow (about 75% of the ₹13 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹244.3 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: Karnataka Bank Ltd. Kodialbail IFSC Code : KARB0000476 Pin Code : 575003. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 300 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
MG Road / city centre299 km
Outer Ring Road / Manyata300 km
Electronic City304 km
Bellandur–Marathahalli belt307 km
Kempegowda Int'l Airport311 km
Whitefield IT hub314 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Land Trades. View Land Trades's full track record →
Land Trades has 17 projects registered in Bangalore, 2 completed.

Other projects by this builder in Bangalore

Land Trades Durga Mahal
Filing overdue · 10% built · 0% sold
Laxmi Govind
Filing overdue · 100% built · 68% sold
Altura
Filing overdue · 100% built · 73% sold
Altitude
Filing overdue · 14% built · 21% sold
Land Trades Krishna Kuteera
Filing overdue · 38% built · 48% sold
Mahalaxmi
Filing overdue · 37% built · 34% sold

Other RERA-registered projects in Koramangala

SJR Primecorporation PVT LTD Palazza PH2
SJR Primecorporation PVT LTD Palazza PH3
SJR Primecorporation PVT LTD Palazzacity

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 16 Jul 2026. Document and inventory dates are shown in their sections.