Registration read 16 Jul 2026Progress & dates
The timeline on file.
Promoter-reported construction
K-RERA quarterly filings · Q3 2025 to Q1 2026
declared completion
Not recorded
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 16 Jul 2026
From another project · Prestige Park Grove
A larger advertised area. Almost the same carpet area.
In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.
This illustrates the report format. These findings concern the named sample, not this project.
Read the sample report ↗
The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1268/378/PR/290325/007641
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Approved plan number | NaGraYoSaNiMy/Vi.Na.A/259/2024-25 | Use this to match the sanctioned drawing set shown by the builder. |
| Plan approval date | 04-05-2024 | |
| Project start date | 01-11-2024 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingNo litigation declared on this project's K-RERA filing.
3 of 20 compliance document slots are filed as Not Applicable; the remaining 17 slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
Statutory approval status
RERA filing0 of 2 applicable approvals are on file; still outstanding: Water supply and sewage board and KPTCL- BESCOM. Confirm each has been granted, not merely applied for, before booking.
9 further authority slots are marked not applicable by the regulator.
| Authority / NOC | Status | Date | File |
|---|---|---|---|
| Water supply and sewage board | To Be Applied | - | View NOC |
| KPTCL- BESCOM | To Be Applied | - | View NOC |
Project team & certifications
RERA filingK-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Chartered accountant | G N Ananthavardhana | 025113 | 2024 | Mysore, Karnataka - 570004 |
| Engineer | Nagaraja B | MYS/BL/10620/24-25 | 2024 | Mysore, Karnataka - 570028 |
Financials & Construction Progress
Financial disclosures
RERA filingLatest quarterly filing (2026-Q1): ₹0.13 Cr collected from buyers, ₹0.17 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹0.17 Cr) exceeded buyer collections (₹0.13 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.
| Construction progress | 70% → 95% (+25 pts) |
| Buyer collections in available QPRs | ₹0.35 Cr |
| Escrow withdrawals in available QPRs | ₹0.28 Cr (0.80x collections) |
- Construction progress moved from 70% to 95% across the filed QPR window.
- The builder has drawn 0.80x of buyer collections from escrow (about 80% of the ₹0 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.
- In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.
QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.
The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.
RERA 70% project account is on file: KOTAK MAHINDRA BANK Saraswathipura, Mysore IFSC Code : KKBK0000425 Pin Code : 570009. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Location & Connectivity
The nearest major job hub is ~131 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Electronic City | 131 km |
| MG Road / city centre | 132 km |
| Outer Ring Road / Manyata | 137 km |
| Bellandur–Marathahalli belt | 138 km |
| Whitefield IT hub | 145 km |
| Kempegowda Int'l Airport | 154 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.