Bangalore/Project record

K-RERA · the public record

SREENIDHI E-CITY

Anekal · SREENIDHI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ3 2025 filing
1units not bookedof 44 · Q3 2025 filing
31 Dec 2025declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q3 2025

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK
36
2 BHK
8

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

0.6registered acres

68.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/091123/006402

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2025
Land area2,608 sq m (0.6 acres)
Homes registered44
Tower/wing entries1
Unit mix36 × 3 BHK, 8 × 2 BHK

In context

Density68.3 homes per acre
Density in context39th percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units44Total inventory registered with K-RERA.
Official carpet area3,782 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area5,476 sqmUseful scale context when comparing density and project cost.
Registered land area2,608 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.74Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)48Separate filed counts; these categories may overlap and are not added together.
Covered-parking field48Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBenapra/Nam/ASA/AA-3/TAS-2/D/05/2023-24Use this to match the sanctioned drawing set shown by the builder.
Plan approval date22-05-2023
Project start date01-07-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK3682%3,230 sqm
2 BHK818%551 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Sreenidhi E-City4444814.95 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 44 official flat/unit rows, matching the 44 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK3681.5-101.7 sqm51.6-62.4 sqm36
2 BHK868.7-69.2 sqm42.6-43.0 sqm8

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Sreenidhi E-City4468.7-101.7 sqm42.6-62.4 sqm44
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
101Sreenidhi E-City13 BHK96.4 sqm61.4 sqm1
102Sreenidhi E-City13 BHK98.8 sqm62.4 sqm1
103Sreenidhi E-City13 BHK84.7 sqm55.1 sqm1
104Sreenidhi E-City13 BHK81.5 sqm51.6 sqm1
105Sreenidhi E-City13 BHK81.5 sqm51.6 sqm1
106Sreenidhi E-City13 BHK84.5 sqm52.2 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 5 of 28 compliance document slots are filed as under process / not yet usable: Board Resolution for Authorized Signatory/Certificate of Authorization, Urban Land Ceiling, District Magistrate, Conversion Certificate under section 95 of the KLR Act 1964, Any other document (Rights/Title/Interest/Name).

3 additional compliance slots are filed as Not Applicable.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2025 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC and environmental clearance are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

7 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved16-03-2023WATER NOC FROM PANCHAYATH.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved29-08-2025CFO APPROVAL CERTIFICATE.pdf
KPTCL- BESCOMApproved28-06-2023BESCOM NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantMallaiah B2077692003Bengaluru Urban, Karnataka - 560070
EngineerARUN KUMAR S RBCCL/BL-3.6/SE-0160/23-242010Bengaluru Urban, Karnataka - 560020
ArchitectG BHANUMATHY94/167502008Bengaluru Urban, Karnataka - 560070
ContractorSREENIDHI DEVELOPERS-2006Bengaluru Urban, Karnataka - 560061

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q3): ₹3.10 Cr collected from buyers, ₹3.93 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹3.93 Cr) exceeded buyer collections (₹3.10 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress100% → 100% (+0 pts)
Units sold/booked as registered43/44 (98%)
Buyer collections in available QPRs₹3.10 Cr
Escrow withdrawals in available QPRs₹3.93 Cr (1.27x collections)
  • 98% of registered units are shown as sold/booked, but no completion certificate is on file yet.
  • The filed unit sales count did not move across the available QPR window because the project was already effectively sold out.
  • Across available QPR rows, escrow withdrawals are 1.27x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹31.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Axis Bank. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Electronic City2 km
Bellandur–Marathahalli belt12 km
MG Road / city centre17 km
Whitefield IT hub19 km
Outer Ring Road / Manyata24 km
Kempegowda Int'l Airport41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sreenidhi Developers.

Other RERA-registered projects in Electronic City

Major developers building in Electronic City

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.