At Prestige Southern Star, construction was reported at 41.0%. At Casagrand Amor, it was 40.0%. Yet their declared completion months sit 19 months apart. The projects’ Q1 2026 quarterly progress filings and completion dates with Karnataka RERA make a useful point for Akshayanagar homebuyers: similar construction percentages cannot rank the declared wait for a home.
That distinction deserves attention as the Pink Line moves towards passenger service. Elets Technomedia reports safety clearance for the elevated section between Kalena Agrahara and Tavarekere. The Indian Express reports that an inauguration date was awaited, placing the network milestone after the section enters service.
For someone visiting homes around the southern stretch, the transport news provides a reason to look. The housing filings provide the basis for choosing. They show projects with substantial recorded purchasing at early construction stages, others with advanced work, and similar construction percentages attached to different completion horizons.
Almost level on construction, different dates
Prestige Southern Star, by PRESTIGE ACRES, carries a September 2029 declared completion date in its K-RERA project record. Casagrand Amor, by CASA GRANDE GARDEN CITY BUILDERS, carries February 2028. Their Q1 2026 QPRs were submitted on 15 July 2026 and 10 July 2026 respectively.
A buyer sorting these homes solely by construction percentage would place them close together. A buyer sorting them by declared completion month would separate them. The 19-month difference matters to a household deciding how long to continue renting or when to arrange a move.
It also changes the questions worth asking at a site visit. Ask what work remains within the registered project, how the reported percentage relates to the building being considered, and what possession date is being offered for the particular flat. The percentage alone cannot establish whether either declared deadline is achievable.
The table pairs each named project’s K-RERA completion record with its Q1 2026 QPR. Sold and total units are shown together so the reported purchasing position can be read in context.
| Project | Filed promoter | Registration number | QPR submitted | Construction | Reported sold / total units | Declared completion |
|---|---|---|---|---|---|---|
| Prestige Southern Star | PRESTIGE ACRES | PRM/KA/RERA/1251/310/PR/210325/007603 | 15 July 2026 | 41.0% | 1902 / 2130 | September 2029 |
| Casagrand Amor | CASA GRANDE GARDEN CITY BUILDERS | PRM/KA/RERA/1251/310/PR/140324/006701 | 10 July 2026 | 40.0% | 335 / 480 | February 2028 |
| Sobha Magnus | SOBHA | PRM/KA/RERA/1251/310/PR/131025/008160 | 13 July 2026 | 9.0% | 272 / 294 | May 2030 |
| Casagrand Hazen | CASA GRANDE GARDEN CITY BUILDERS | PRM/KA/RERA/1251/310/PR/220722/005099 | 14 July 2026 | 78.0% | 618 / 622 | July 2027 |
| Pruthvi Homes | PRUTHVI PROJECTS | PRM/KA/RERA/1251/308/PR/150224/006623 | 15 July 2026 | 98.0% | 17 / 32 | December 2026 |
These are dated declarations: locality labels do not establish station walking access, completion dates do not confirm possession, and reported sold figures do not establish current availability or sales velocity.
Kalena Agrahara offers a wider construction range
Sobha Magnus, Casagrand Hazen and Pruthvi Homes provide a focused comparison within Kalena Agrahara. The chart selects these projects because each has a Q1 2026 construction filing and a declared completion date available for the same locality comparison.
Reported construction in selected Kalena Agrahara projects
percent construction complete
Source: Each named project's Q1 2026 K-RERA QPR; submission dates in the table
Here, the construction stages and completion horizons run in the same direction. Magnus pairs 9.0% construction with May 2030; Hazen pairs 78.0% with July 2027; Pruthvi pairs 98.0% with December 2026. Those combinations, from their respective K-RERA QPRs and project records, give households distinct starting points for a shortlist.
The purchasing figures add another dimension. Magnus reported 272 sold out of 294 units, or 92.52%. Hazen reported 618 out of 622, or 99.36%. Pruthvi reported 17 out of 32, or 53.13%. Pruthvi’s more advanced reported construction therefore sits alongside a smaller recorded sold share than either comparator. A household seeking advanced construction should assess that stage directly, without using the sold share as a substitute.
Hazen’s work advanced with the same endpoint sold count
Casagrand Hazen reported 68.0% construction in its Q3 2025 K-RERA QPR, submitted on 12 January 2026. Its Q1 2026 filing reported 78.0%. Both recorded 618 sold out of 622 units. Physical progress changed even though the sold count at those endpoints was identical.
Sobha Magnus showed a different combination. Its Q3 2025 K-RERA QPR, submitted on 12 January 2026, reported 3.0% construction and 231 sold out of 294 units. Its Q1 2026 filing reported 9.0% construction and 272 sold. Reading the measures separately preserves what each actually describes: building progress and recorded purchasing.
Put the moving plan beside the filing
Akshayanagar supplies the important counterpoint to Kalena Agrahara’s construction range. Southern Star’s and Amor’s closely matched percentages accompany substantially different declared completion months. That prevents a tempting shortcut: treating a more advanced percentage as an automatic promise of earlier possession.
Start with the period in which the household wants to move. Compare that with the registered completion date, then examine the dated construction history and the proposed possession date for the flat. Discuss payments against that sequence. Finally, travel from the project entrance to the station entrance you expect to use.
The Pink Line can make these neighbourhoods more relevant to a home search. The strongest purchase decision will still come from matching a particular home’s filed progress and completion horizon to the household that intends to live there.