Bangalore/Project record

K-RERA · the public record

SOBHA MAGNUS

Bengaluru South · SOBHA

Is this the right project?
Which home should you choose?

Read the free RERA facts below. For help choosing a home or comparing a price, select a report.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
9%construction reportedQ1 2026 filing
22units not bookedof 294 · Q1 2026 filing
31 May 2030declared completionK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 May 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 25 Oct 2026

Registered units and project size

3 BHK
252
4 BHK
38
2 BHK
4

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

5.8registered acres

50.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for SOBHA MAGNUS

K-RERA · PRM/KA/RERA/1251/310/PR/131025/008160

Project facts and comparisons

On the register

Declared completion31 May 2030
Land area23,669 sq m (5.8 acres)
Homes registered294
Tower/wing entries5
Unit mix252 × 3 BHK, 38 × 4 BHK, 4 × 2 BHK

In context

Density50.3 homes per acre
Density in context18th percentile of 791 Bengaluru South projects (median 77.3)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units294Total inventory registered with K-RERA.
Official carpet area37,513 sqmTotal carpet area reported for the project.
Official built-up area79,932 sqmUseful scale context when comparing density and project cost.
Registered land area23,669 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries5Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)514Separate filed counts; these categories may overlap and are not added together.
Covered-parking field514Separate filed counts; these categories may overlap and are not added together.
Open-parking field5Separate filed counts; these categories may overlap and are not added together.
Garage field2Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/Addl.Dir/JDSOUTH/0026/25-26Use this to match the sanctioned drawing set shown by the builder.
Plan approval date10-10-2025
Project start date01-10-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK25286%30,953 sqm
4 BHK3813%6,254 sqm
2 BHK41%306 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Sobha Magnus Phase 1 - Block 1 - Wing 0195811029.95 m
Sobha Magnus Phase 1 - Block 2 - Wing 0295910029.95 m
Sobha Magnus Phase 1 - Block 2 - Wing 0395910029.95 m
Sobha Magnus Phase 1- Block 3 - Wing 0495910029.95 m
Sobha Magnus Phase 1- Block 3 - Wing 0595910429.95 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 294 official flat/unit rows, matching the 294 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK25294.3-146.0 sqm48.2-77.4 sqm252
4 BHK38164.6 sqm85.7 sqm38
2 BHK476.5 sqm41.5 sqm4

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Sobha Magnus Phase 1 - Block 2 - Wing 025976.5-136.0 sqm41.5-69.5 sqm59
Sobha Magnus Phase 1 - Block 2 - Wing 035976.5-136.0 sqm41.5-69.5 sqm59
Sobha Magnus Phase 1- Block 3 - Wing 045976.5-136.0 sqm41.5-69.5 sqm59
Sobha Magnus Phase 1- Block 3 - Wing 055976.5-164.6 sqm41.5-85.7 sqm59
Sobha Magnus Phase 1 - Block 1 - Wing 0158116.8-164.6 sqm61.8-85.7 sqm58
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1001Sobha Magnus Phase 1 - Block 1 - Wing 0104 BHK164.6 sqm85.7 sqm1
1003Sobha Magnus Phase 1 - Block 1 - Wing 0103 BHK136.0 sqm69.5 sqm1
1004Sobha Magnus Phase 1 - Block 1 - Wing 0103 BHK136.0 sqm69.5 sqm1
1005Sobha Magnus Phase 1 - Block 1 - Wing 0103 BHK116.8 sqm61.8 sqm1
1006Sobha Magnus Phase 1 - Block 1 - Wing 0104 BHK164.6 sqm85.7 sqm1
1011Sobha Magnus Phase 1 - Block 1 - Wing 0114 BHK164.6 sqm85.7 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

1 of 28 compliance document slots are filed as Not Applicable; the remaining 27 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

See the filed approval statuses and linked documents →

Complaints on this project's K-RERA page (127 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190217/0002175
17-02-2019
Compensation for Delay of projectsSobha City - Casa Paradiso Block 4 (another project by this promoter)DISPOSED AO
CMP/190218/0002166
18-02-2019
Refund of booking amountSobha Dream Acres - Palm Springs Phase 17 Wing 54 (another project by this promoter)DISPOSED AO
CMP/190225/0002263
25-02-2019
Refund of Advance amount-Sobha Arena - The Park ( Block 2 ) (another project by this promoter)DISPOSED AO
CMP/190308/0002388
08-03-2019
Non-allotment of agreed units & RefundSobha Indraprastha (another project by this promoter)DISPOSED AO
CMP/190308/0002322
08-03-2019
Promoter SL Demanding 38% payment of unit cost before entering the ATSSobha Arena - Pebble Court (Block 1) (another project by this promoter)DISPOSED AO
CMP/190315/0002219
15-03-2019
About refund of booking amountSobha Dream Acres - Tropical Greens Phase 8 Wing 43 and 44 (another project by this promoter)DISPOSED AO
CMP/190324/0002505
24-03-2019
Compensation against late deliverySobha City - Casa Paradiso Block 4 (another project by this promoter)DISPOSED AO
CMP/190401/0002556
01-04-2019
Please refund booking amountSobha Dream Acres - Rain Forest Phase 2 Wing 3 and 4 (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

4 of 4 applicable approvals are marked Approved in the filing. Check the linked documents for their scope and validity.

6 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved11-07-2024BWSSB NOC Magnus 11072024.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved26-12-2024CFE Magnus 26122024.pdf
KPTCL- BESCOMApproved21-05-2024BESCOM NOC Magnus 21052024.pdf
Fire and SafetyApproved29-11-2024Fire NOC Magnus 29112024.pdf

Project team & certifications

RERA filing

K-RERA names 5 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantBalaji D2173902016Bengaluru Urban, Karnataka - 560084
EngineerMr. Srinivas SathyanarayanM-17239731995Bengaluru Urban, Karnataka - 560103
EngineerBalakrishnan GF-124976-92019Bengaluru Urban, Karnataka - 560103
ArchitectGeetha K NairCA/93/156411993Bengaluru Urban, Karnataka - 560103
ContractorSobha Limited-1995Bengaluru Urban, Karnataka - 560103

Builder track record

RERA filing

Sobha has 121 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Sobha”) (average reported construction progress 62%). 60 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹36.70 Cr collected from buyers, ₹33.05 Cr withdrawn from the project's escrow account.

Construction progress3% → 9% (+6 pts)
Units sold/booked as registered272/294 (93%)
Buyer collections in available QPRs₹161.92 Cr
Escrow withdrawals in available QPRs₹140.04 Cr (0.86x collections)
  • Construction progress moved from 3% to 9% across the filed QPR window.
  • The builder has drawn 0.86x of buyer collections from escrow (about 86% of the ₹162 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹102.2 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: RATNAKAR BANK RESIDENCY ROAD IFSC Code : RATN0000156 Pin Code : 560025. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 9 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Electronic City9 km
MG Road / city centre11 km
Bellandur–Marathahalli belt13 km
Outer Ring Road / Manyata19 km
Whitefield IT hub21 km
Kempegowda Int'l Airport38 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sobha. View Sobha's full track record →
Sobha has 120 projects registered in Bangalore, 25 completed.
276 complaints on the K-RERA register against Sobha in Bangalore.

Buyer reviews · MouthShut

★★☆☆☆ 1.6/5

337 reviews for Sobha in Bangalore
Read 337 reviews on MouthShut →

Other projects by this builder in Bangalore

ONE Residences AT Sobha ONE World Ph1 W1 And 2
Filing overdue · 28% sold
ONE Residences AT Sobha ONE World Ph2 W3 And 4
Filing overdue · 0% sold
ONE Residences AT Sobha ONE World Ph3 W5 And 6
Filing overdue · 0% sold
ONE Residences AT Sobha ONE World Ph4 W7 And 8
Filing overdue · 17% sold
ONE Residences AT Sobha ONE World Ph5 W9,10,11
Filing overdue · 48% sold
ONE Residences AT Sobha ONE World Ph6 W12,13,14
Filing overdue · 44% sold

Other RERA-registered projects in Hulimavu

Major developers building in Hulimavu

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.