Developer RERA record

Adarsh

Adarsh has 28 RERA-registered projects: 2 projects under construction, Bengaluru averaging 60% construction; 16 projects past their declared completion date. All figures are the developer's own regulator filings.

2
Under construction
16
Past declared date
85%
Bengaluru inventory booked
29
RERA complaints filed

Public registration records

These records have not been classified as delivered, under construction or overdue. The declared date and status are filings, not a current site inspection.

CELESTIAL LIVING

Ahmedabad · Registered: 2019-03-01 · Declared completion: 2024-01-31 · Filed status: New

AURANIA

Ahmedabad · Registered: 2025-03-19 · Declared completion: 2028-07-28 · Filed status: New

Adarsh Ratna

Ahmedabad · Registered: 2025-01-23 · Declared completion: 2030-04-30 · Filed status: New

WONDER VISTA

Hyderabad region · Declared completion: 2028-10-16

Under construction

Under construction — 2 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
Adarsh Welkin Park VillasBengaluru58%
ADARSH PALM ACRES PHASE 3Bengaluru2%
Considering a specific Adarsh project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (16)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
SAI CRYSTALBengaluru2025-06
Adarsh Palm Acres - Phase 2-Part BBengaluru2020-11
Adarsh Palm Acres - Phase 2-Part ABengaluru2019-11
Adarsh Palm Acres - Phase 1-Part ABengaluru2019-11
Adarsh Palm Acres - Phase 1-Part BBengaluru2020-11
V-REGALIAABengaluru2024-09
ADARSH GREENS PHASE 1 (99.0% built)Bengaluru2024-10
Adarsh Premia - Phase 1 (84.0% built)Bengaluru2020-06
Adarsh CitrineBengaluru2018-08
Palm Meadows AnnexeBengaluru2020-11
ADARSH ASTRIABengaluru2022-02
ADARSH STRATUSS PHASE 1 (75.0% built)Bengaluru2024-02
Palm Meadows Extension Phase-2Bengaluru2020-07
ADARSH CREST PHASE 1 (74.0% built)Bengaluru2025-12
ADARSH GREENS PHASE 2 (90.0% built)Bengaluru2025-05
DIGITOWN PHASE-1Noida2026-09
Registered, no progress filed yet (3)click to expand
ProjectCity
KALYANI LAYOUTBengaluru
ADARSH LAKE RESERVA Phase 1Bengaluru
DIGITOWN-IINoida

RERA complaints & orders

Regulatory record

29 total complaints filed — above average for builders we track (79th percentile).

28
MahaRERA complaints
1
Karnataka RERA complaints

Most recent orders on the RERA register:

ProjectComplainantBenchDate
LINKPARKVeena Dwarkadas BajajHON. MEMBER ICopyright

Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.

Figures are Adarsh's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.