Gurgaon/Project record

HRERA · the public record

Colonnade

SECTOR-66, VILLAGE BADSHAHPUR , GURUGRAM · Emaar Mgf Land

Is this the right project?
Which unit should you choose?

Read the free RERA facts below. For help choosing a unit or comparing a price, select a report.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
322units in latest filingQ1 2026 filing
0units sold that quarterQ1 2026 filing
31 Dec 2023registration expiryHRERA registration · read 22 Oct 2026

Free project details

Registration read 22 Oct 2026

RERA details for Colonnade

HRERA ·

Escrow account

What has moved through the RERA escrow account?

Across 6 filed quarterly reports, Colonnade records ₹5.55 Cr paid into and ₹5.80 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹2 L.

₹5.55 Cr

into the escrow account

₹5.80 Cr

withdrawn

₹2 L

latest balance

Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.

Source · HRERA quarterly progress reports

Sales Traction, Quarter by Quarter

Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.

QuarterUnits bookedTotal units
2024 Q40322
2025 Q10322
2025 Q20322
2025 Q30322
2025 Q40322
2026 Q10322

Escrow Account Activity

Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.

QuarterDepositedWithdrawnBalance
2024 Q4₹3.95 Cr₹4.00 Cr₹22 L
2025 Q1₹85 L₹1.00 Cr₹6 L
2025 Q2₹1 L₹0 L₹8 L
2025 Q3₹3 L₹0 L₹11 L
2025 Q4₹13 L₹0 L₹24 L
2026 Q1₹58 L₹80 L₹2 L

Builder Record

Emaar MGF has 21 other Gurgaon projects on the HRERA register; 1 is past the declared completion date with no OC yet, 18 delivered. Read it as a spot-check list for a pattern, not a delay rate.

  • Capital Towers — declared 2020-07-31 · OC on record
  • Emaar Business District 65 — declared 2024-08-31 · OC on record
  • Emaar Digihomes — declared 2024-03-31 · OC on record
  • Emerald Classic — declared 2022-12-31 · OC on record

Location & Connectivity

The nearest of the listed job hubs is about 7 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Golf Course Road belt7 km
Cyber City / DLF Cyber Hub11 km
Udyog Vihar12 km
IMT Manesar12 km
IGI Airport, Delhi18 km
Connaught Place, Delhi30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Emaar MGF. View Emaar MGF's full track record →
Emaar MGF has 21 projects registered in Gurgaon, 19 completed.

Other projects by this builder in Gurgaon

Capital Towers
Completed · 80% sold
Emaar Business District 65
Completed
Emerald Estate
Completed · 99% sold
Emerald Hills
Completed · 91% sold

Other RERA-registered projects in Sector 66

Major developers building in Sector 66

Figures are the developer's own quarterly disclosures on the Haryana RERA register. "Sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Gurgaon project-health tool.

Registration last seen on RERA: 22 Oct 2026. Document and inventory dates are shown in their sections.