Mumbai/Project record

MahaRERA · the public record

16 MOUNT BLANC

Mumbai Suburban · MOUNT BLANC REAL ESTATE LLP

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2019declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for 16 MOUNT BLANC

MahaRERA · P51800005179

Delivery and registration

When is the project declared for completion?

16 MOUNT BLANC is registered with MahaRERA as P51800005179 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

82months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800005179
Registered on10 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 82 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for 16 MOUNT BLANC record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for 16 MOUNT BLANC in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
16 MOUNT BLANC - A WING1G+14-
16 MOUNT BLANC - B WING1G+14-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for 16 MOUNT BLANC, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019882127/10/2021DR VISHWANATH VASANT PUJARI vs MOUNT BLANC REAL ESTATES LLPorder passed
CC00600000019885028/10/2021SHASHANK SUDHAKAR DHOND vs Mount Blanc Real Estate LLPorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019Society Name: Tilak Vaibhav Co Op Hsg Soc Ltd, Building No. 16, CTS No. 19(PT), Tilak Nagar, Chembur, Mumbai 400089 Project name: 16 Mount Blanc Developer Name: Mou
31 Dec 201931 Dec 2019After registration in RERA on 10.08.2017, we hope that submitted file would be cleared from Building proposal within one month and building would be completed by all respect and we

Location, Land & Connectivity

Located at Mumbai, Mumbai Suburban, 400089. Per the filed land record, the plot is bounded to the north by OPEN SPACE OF MHADA 60FT ROAD, to the south by BUILDING NO - 17, to the east by BUILDING N0 - 15 and to the west by 50FT WIDE ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 3 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district11 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chembur

Orient Regency Building No. 1
declared completion Dec 2026 · Orient Combine
Sree Sudarshan Heights
declared completion Dec 2026 · AUM SAI Constructions Private Limited
Srushtiraj Tower
declared completion Dec 2026 · Chinnaiah Venkatesh Gowda
Promesa Midtown
declared completion Dec 2026 · Darshan Properties
Vishwasangam
declared completion Dec 2026 · Vishwashakti Cooperative Housing Society
Ampple-ONE
declared completion Mar 2027 · Amppletech Projects Private Limited
More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

16th Avenue
declared completion Jun 2018 · MNK Builders LLP
17 West
declared completion Dec 2027 · Strive Realty LLP
18th Avenue
declared completion Dec 2029 · Blueladder Buildcon LLP
19 Degree North
declared completion Jun 2026 · Arunis Edifice Private Limited
21 Business Elites
declared completion Jan 2026 · Amar Amrut Infra LLP
22 Alliance House
declared completion Dec 2028 · Alliance City Developers Realtors PVT LT

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.