Amisha Empire - Phase I
Hatkesh · Amisha Associates
Project Review · example purchase
Spending a few crores on a unit? ₹4,999 to check what you’re buying.
Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.
See the report before you buy
Avoid bad decisions, only go for the best units.
Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.
Read the Project Review sample ↗From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗Free project details
Registration read 18 Jul 2026RERA details for Amisha Empire - Phase I
MahaRERA · P51700010847
Delivery and registration
When is the project declared for completion?
Amisha Empire - Phase I is registered with MahaRERA as P51700010847 and the promoter has declared completion for 30 Jun 2022.
30 Jun 2022
declared completion
52months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 18 Jul 2026
| MahaRERA registration | P51700010847 |
| Registered on | 31 Aug 2017 |
| Promoter-declared completion | 30 Jun 2022 |
| Current status | Certificate Signed |
| Against today | about 52 months past the declared date |
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for Amisha Empire - Phase I in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 18 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| Wing A | 1 | G+12 | 31 Dec 2019 |
| Wing B | 1 | G+15 | 31 Dec 2019 |
| Wing C | 1 | G+12 | 31 Dec 2019 |
Legal and disputes
What disputes are disclosed?
4 complaints are on the MahaRERA record for Amisha Empire - Phase I, with orders passed in 3 of them.
4complaints
3with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 18 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000090157 | 13/08/2019 | DR SAGAR S NALE vs AMISHA ASSOCIATES | order passed |
| CC006000000100554 | 17/08/2019 | RAHUL S PABALE vs amisha associates | order passed |
| CC12401256 | 28/12/2024 | SHAZIYA MOHAMMED SABIR ANSARI vs Amisha Associates | order passed |
| CC12601231 | 06/03/2026 | Meena Mohit Sharma vs Amisha Associates | pending / no order on file |
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 30 Dec 2020 | The Delay in completion of project is because of MBMC not issuing amendment without ULC department clearance and since the matter was pending in Supreme Court and so now we can get |
| 30 Dec 2020 | 31 Dec 2021 | Herewith attached Form E |
Location, Land & Connectivity
Located at Hatkesh, Mira Bhayandar Road, Thane, Thane, 401107. Per the filed land record, the plot is bounded to the north by Mira Bhayandar Road, to the south by Mansarovar Complex, to the east by Open Plot and to the west by Konkan Division. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest of the listed job hubs is about 17 km in a straight line from the mapped location. Road distance and travel time will differ.
| Landmark | Straight-line |
|---|---|
| Andheri MIDC / SEEPZ | 17 km |
| Powai / Hiranandani business park | 18 km |
| Chhatrapati Shivaji Int'l Airport | 21 km |
| Bandra Kurla Complex (BKC) | 24 km |
| Lower Parel / Worli business district | 32 km |
| Nariman Point / Fort | 40 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.