Mumbai/Project record

MahaRERA · the public record

ANANYA RESIDENCY

Mumbai City · SAHYOG GROUP

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2025declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for ANANYA RESIDENCY

MahaRERA · P99000014153

Delivery and registration

When is the project declared for completion?

ANANYA RESIDENCY is registered with MahaRERA as P99000014153 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

10months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000014153
Registered on09 Nov 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ANANYA RESIDENCY record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Promoter record

What else is this promoter on record for?

SAHYOG GROUP is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ANANYA RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
WING D1G+430 Jun 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022DUE TO LOCKDOWN THE WORK WAS STOPPED AND EXTENSION IS REQUIRED.
30 Jun 202231 Dec 2025DUE TO SOME UNAVOIDABLE REASONS THE PROJECT COULD NOT BE COMPLETED IN TIME

Location, Land & Connectivity

Located at Ward ABCD, Mumbai City, 401404. Per the filed land record, the plot is bounded to the north by GUT NO 172, to the south by GUT 77 AND 157, to the east by GUT 76 AND 167 and to the west by GUT NO 165. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 69 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ69 km
Powai / Hiranandani business park71 km
Chhatrapati Shivaji Int'l Airport74 km
Bandra Kurla Complex (BKC)76 km
Lower Parel / Worli business district84 km
Nariman Point / Fort92 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Palghar

Shiv Krupa
declared completion Oct 2026 · Shivaay Realty
V Square Arcade
declared completion Oct 2026 · V Square
Nisarg Shrushti Phase-2
declared completion Nov 2026 · Arvel Realtors
Aloha
declared completion Nov 2026 · SEA Crests Buildcon LLP
Paramount Enclave Phase -1
declared completion Nov 2026 · Kavita Realty Housing LLP
Solitaire Park
declared completion Nov 2026 · Park Solitaire Lifespaces LLP
More builders in Palghar

Major developers building in Palghar

More projects in Palghar

Other RERA-registered projects in Palghar

Ananya Residency
declared completion Mar 2023 · Shreeji Builders
Ananya Residency Wing B Building 3
declared completion Dec 2021 · Vinay Harihar Singh
Angel Apartment
declared completion Dec 2029 · Shreenathji Enterprises
Angel Business Centre
declared completion Jun 2023 · Angel Developers
Angel Crescenta
declared completion Jun 2027 · JD Infra
Angel Homes
declared completion Dec 2029 · Shreenathji Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.