DAISY GARDENS SURVEY NO 12 PHASE I

KHOJ GAON · ANKITA BUILDERS

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

41units filed as unsoldInventory · 22 October 2026
30 Jun 2027declared completionMahaRERA registration · read 18 Jul 2026
113registered unitsMahaRERA registration · read 18 Jul 2026

From another project · Empire Solitaire

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Empire Solitaire Project Review · first page
First page of the complete sample.

Free project details

Registration read 18 Jul 2026

RERA details for DAISY GARDENS SURVEY NO 12 PHASE I

MahaRERA · P51700009528

Delivery and registration

When is the project declared for completion?

DAISY GARDENS SURVEY NO 12 PHASE I is registered with MahaRERA as P51700009528 and the promoter has declared completion for 30 Jun 2027.

30 Jun 2027

declared completion

8months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700009528
Registered on22 Aug 2017
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today8 months to the declared date

Promoter record

What else is this promoter on record for?

ANKITA BUILDERS is the promoter of record on 4 projects registered with MahaRERA.

4projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Construction

How much construction cost has been reported?

In DAISY GARDENS SURVEY NO 12 PHASE I, ₹54.30 Cr of a declared ₹54.30 Cr estimated project cost is reported as incurred, about 100.0%, as at the last certified filing with MahaRERA.

100.0%

₹54.30 Cr

of ₹54.30 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 18 Jul 2026

Sales

How many are filed as sold or booked?

In DAISY GARDENS SURVEY NO 12 PHASE I, 72 of 113 homes filed with MahaRERA are recorded as sold or booked, about 64%, and 41 are filed as unsold.

64%sold or booked

72 of 113 homes

₹19.19 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹16.49 Cr (about 86%) is recorded as collected and ₹26.64 Lakh as receivable.

Source · MahaRERA sold/unsold inventory filing · read 18 Jul 2026

Filed agreement values: across 72 sold or booked entries with usable filed values and areas, the effective carpet rate is ₹6,081/sqft, with eight in ten falling between ₹5,152 and ₹6,628 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 22 October 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific home. On this project 72 homes carry one, and 41 of the 113 are recorded unsold.

Here is one home filed as unsold, beside the amounts filed for comparable homes:

HomeCarpetFiled comparisonBased on
BUILDING NO 10-103377 sqftRs 23.00 lakh typical, over Rs 16.80 lakh to Rs 32.00 lakh57 filed · similar area (within 2%), elsewhere in project

A filed consideration is the amount the promoter reported for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In DAISY GARDENS SURVEY NO 12 PHASE I, 30 of the 41 unsold homes have filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.

See the other 40 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 113 homes are registered across the project.

BuildingWingsFloorsUnitsDeclared completion
BUILDING NO 101G+83730 Dec 2021
BUILDING NO 111G+83830 Dec 2021
BUILDING NO 121G+83830 Dec 2021

Unit mix on the filing: 113 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 5 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2021The project is under construction. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to
30 Dec 202130 Jun 2023The project is under construction. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to
30 Jun 202330 Jun 2024The project is under construction & we have completed almost work on the project. However due to imposition of lockdown and consequently migration of labour and contractors we are
30 Jun 202430 Jun 2026The project is completed in all aspects and we had applied for Occupancy Certificate. However for the Purpose of RERA Compliances we have applied for extension of Project due to ex
30 Jun 202630 Jun 20271) Slow booking response from customer. 2) Because of slow down in booking response, we have work/act accordingly in above said building. But at present, we have completed our 9

Location, Land & Connectivity

Located at KHOJ GAON, KAMLAKAR NAGAR, Ulhasnagar, Thane, 421505. Per the filed land record, the plot is bounded to the north by SURESH JADHAV LAND, to the south by SURVEY NO 11, to the east by KATWADI and to the west by SURVEY NO 15 HISSA NO 7. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 35 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park35 km
Andheri MIDC / SEEPZ38 km
Chhatrapati Shivaji Int'l Airport40 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district47 km
Nariman Point / Fort52 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chikhloli

Nidhi Residency
declared completion Mar 2027 · Aditya Yash Builders
Shreeji Landmark Phase 1
declared completion Mar 2027 · Deep Laxmi Associates
Daisy Gardens Building No.13
declared completion Jun 2027 · Ankita Builders
Patels Eternity
declared completion Nov 2027 · Omkar Infrastructure
Madhukar Heritage Building A-1
declared completion Dec 2027 · Madhukar Valku Rasalpatil
Matoshree Nagar Excellency Bldg Sapphire A AND Bldg Pearl B
declared completion Dec 2027 · Matoshree Shelters Private Limited
More builders in Chikhloli

Major developers building in Chikhloli

More projects in Thane

Other RERA-registered projects in Thane

Daksh Palace
declared completion Sep 2024 · Thakur Developers
Dalal Kalash
declared completion Dec 2027 · Advance Buildcon
Dalals Square
declared completion Sep 2026 · Dalal Realty
Dalvi Amigo
declared completion Dec 2028 · Rupesh Ramesh Dalvi
Damji Shamji Galleria
declared completion Dec 2028 · Vinayak Developers
Damodar Tower
declared completion Mar 2027 · Jaanvi Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.