Mumbai/Project record

MahaRERA · the public record

EL SIGNORA

ADARSH NAGAR · PARAS BUILDERS (1985)

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
28 Feb 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for EL SIGNORA

MahaRERA · P51800005086

Delivery and registration

When is the project declared for completion?

EL SIGNORA is registered with MahaRERA as P51800005086 and the promoter has declared completion for 28 Feb 2023.

28 Feb 2023

declared completion

44months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800005086
Registered on09 Aug 2017
Promoter-declared completion28 Feb 2023
Current statusCertificate Signed
Against todayabout 44 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for EL SIGNORA record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for EL SIGNORA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25.

BuildingWingsFloorsDeclared completion
SHIV SFURTI SRA CHS LTD REHAB BLDG NO 21G+2331 Mar 2021
EL SIGNORA SALE BLDG 31G+2530 Mar 2022

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for EL SIGNORA, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019892910/11/2021Prakash Vishram Bane vs Paras Builder (1985)order passed
CC00600000020976729/01/2022Mr. Shivanna M Shetty vs M/s Paras Builders (1985)order passed
CC00600000020972404/02/2022PARADIGM EVOLVERS LLP vs RONGOM TAGORE MUKERJIorder passed
CC00600000033383930/12/2022Mr Rongom Tagore Mukherji vs Paradigm Evolvers LLPorder passed
CC00600000037512612/04/2023Paras Builders 1985 vs Manoj Kumar Pandeyorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered28 Feb 2023The Developer is implementing the slum rehabilitation scheme by constructing 2 rehab buildings and one Sale building No. 3 (“EL Signora Project”). The completion of the scheme has

Location, Land & Connectivity

Located at ADARSH NAGAR, OFF NEW LINK ROAD, Andheri, Mumbai Suburban, 400102. Per the filed land record, the plot is bounded to the north by D P ROAD, to the south by CTS 35 PT, to the east by D P ROAD and to the west by CTS 31 AND 35 PT. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 4 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport7 km
Powai / Hiranandani business park8 km
Bandra Kurla Complex (BKC)10 km
Lower Parel / Worli business district16 km
Nariman Point / Fort24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Jogeshwari West

Lashkaria Pearl
declared completion Nov 2026 · Lashkaria Housing & Infrastructure P
A H Avenue
declared completion Dec 2026 · A.h. Constructions
KEY Tech Park
declared completion Dec 2026 · M/s Keytech
Universal Garden- B Wing
declared completion Dec 2026 · Pagarani Universal Infrastructure Pvt Lt
Agaa Residency
declared completion Dec 2026 · Agaa Enterprises
Dream Aspire
declared completion Dec 2026 · Dream India Builders
More builders in Jogeshwari West

Major developers building in Jogeshwari West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Elanza Commercial
declared completion Dec 2027 · Acme Complex Pvt Ltd
Elegance Heights
declared completion Dec 2029 · SGF Enterprises
Elegant Residency
declared completion Dec 2026 · Elegant Builders AND Developers
Element 7 8
declared completion Apr 2028 · Agastya Infra
Elenora
declared completion Sep 2026 · Parinee VIR Bhuvan Redevelopment Private
Elevate 9
declared completion Mar 2031 · Meru Realty LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.