GURU OMKAR CHSL

Borivali · SISCORN DEVELOPERS & BUILDERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for GURU OMKAR CHSL

MahaRERA · P51800012773

Delivery and registration

When is the project declared for completion?

GURU OMKAR CHSL is registered with MahaRERA as P51800012773 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

40months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800012773
Registered on07 Sep 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 40 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GURU OMKAR CHSL record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GURU OMKAR CHSL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
GURU OMKAR1G+830 Oct 2020

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for GURU OMKAR CHSL, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000050066202/06/2024Gautam Purshottam Kabadi vs Siscorn Developers And Buildersorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020The proposed project is a redevelopment project under DCR 33(7). From September, 2018 DCR 2034 replaced DCR 1991, but the rules are yet to be implemented. Our project was commenced
30 Apr 202031 Dec 2022The outbreak of Covid-19 Pandemic and restriction imposed by Government and Local Authorities from time to time has hindered our Project. Due to restrictions on movement of laborer

Location, Land & Connectivity

Located at Borivali, Borivali, Borivali, Mumbai Suburban, 400068. Per the filed land record, the plot is bounded to the north by SHANTI KISHAN CHSL, to the south by W S ROAD, to the east by DUTTA KRUPA CHSL and to the west by SAVITRI DHAM CHSL. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 15 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ15 km
Powai / Hiranandani business park17 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)22 km
Lower Parel / Worli business district29 km
Nariman Point / Fort37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dahisar East

Jeandveekedarnath
declared completion Dec 2026 · JE AND VEE Infrastructure
Shri Upendra Chsl
declared completion Dec 2026 · Harshal Enterprises
Swayam Niketan
declared completion Dec 2026 · Jainam Associates
A And O Eminente
Not filing quarterly progress reports · declared completion Dec 2026 · Ashapura Housing Private Limited
Amber Heights
declared completion Dec 2026 · Ghanshyam Enterprises
Ashtha Sharon Dahisar West
declared completion Dec 2026 · Indo Build Enterprise
More builders in Dahisar East

Major developers building in Dahisar East

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Guru Shanti Niwas
declared completion Dec 2029 · SRP Realtors Privaye Limited
Gurukripa
declared completion Sep 2026 · Inspira Realty And Infra Private Limited
Gurukrupa CHS
declared completion Jun 2022 · Metaface India PVT LTD
Gurukrupa Dhyanam
declared completion Mar 2027 · Gurukrupa Realcon Infrabuild LLP
Gurukrupa Ekam
declared completion Apr 2029 · Gurukrupa Realcon Infrabuild LLP
Gurukrupa Gangav
declared completion Jun 2024 · Gurukrupa Realcon Developers Private Lim

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.