KANTAI HEIGHTS

THAKURLI · ANANNYA BUILDERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for KANTAI HEIGHTS

MahaRERA · P51700019155

Delivery and registration

When is the project declared for completion?

KANTAI HEIGHTS is registered with MahaRERA as P51700019155 and the promoter has declared completion for 31 Dec 2022.

31 Dec 2022

declared completion

46months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700019155
Registered on09 Jan 2019
Promoter-declared completion31 Dec 2022
Current statusCertificate Signed
Against todayabout 46 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KANTAI HEIGHTS record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KANTAI HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
KANTAI HEIGHTS1G+630 Jun 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2021Due to COVID 19 work has been delayed. We would like to clarify that within the above mentioned date the project will be completed. We have attached architect certificate.
30 Jun 202131 Dec 2022We have been grappled with shortage of labour and a demand slump challenges triggered by the second wave of covid and the resulting lockdown. The past year 2020-21, has been partic

Location, Land & Connectivity

Located at THAKURLI, THAKURLI, Kalyan, Thane, 421201. Per the filed land record, the plot is bounded to the north by ADIK KRISHNA, to the south by 9 MTR WIDE DP ROAD, to the east by RAMJI SMRUTI and to the west by DATTA DARSHAN BUILDING. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivli East

Shanu Majestic
declared completion Dec 2026 · Fortune Group Of Construction
Balaji Annex
declared completion Dec 2026 · M/S OM Swayambhu Siddhivinayak Builders
Leela Shankar Residency
declared completion Dec 2026 · Ekveera AAI Construction
Ram Janaki
declared completion Dec 2026 · Shree Ganesh Enterprises
UMA Lambodar Heights
Not filing quarterly progress reports · declared completion Dec 2026 · Shree RAJ Properties Developers
Aditya Heights
declared completion Dec 2026 · Ashapura Developers
More builders in Dombivli East

Major developers building in Dombivli East

More projects in Thane

Other RERA-registered projects in Thane

Kapil Bling
declared completion Mar 2026 · Not Available
Kapil Continental
declared completion Dec 2029 · Sacvir Realtors LLP
Kapil Paradise
declared completion Dec 2025 · Pradeep Raghunath Patil
Kapleshwara Residency
declared completion Dec 2029 · Kapleshwara Homes LLP
Karnika Galaxy Phase 2
declared completion Dec 2028 · Patil Developers
Karniks Exotica
declared completion Jan 2021 · Karniks Exotica

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.