KARRM PANCHTATVA-3

Mumbai Suburban · KARRM INFRASTRUCTURE PRIVATE LIMITED

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for KARRM PANCHTATVA-3

MahaRERA · P51700007680

Delivery and registration

When is the project declared for completion?

KARRM PANCHTATVA-3 is registered with MahaRERA as P51700007680 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700007680
Registered on17 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KARRM PANCHTATVA-3 record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.

Promoter record

What else is this promoter on record for?

KARRM INFRASTRUCTURE PRIVATE LIMITED is the promoter of record on 5 projects registered with MahaRERA.

5projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KARRM PANCHTATVA-3 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
B11G+731 Dec 2022
B71G+731 Dec 2022
B81G+731 Dec 2022
B91G+731 Dec 2022
B101G+731 Dec 2022
B111G+731 Dec 2022
C11G+731 Dec 2022
C21G+731 Dec 2022
C31G+731 Dec 2022
C41G+731 Dec 2022
C51G+731 Dec 2022
C61G+731 Dec 2022
D11G+731 Dec 2022
D71G+731 Dec 2022
D81G+731 Dec 2022
B21G+731 Dec 2022
B31G+731 Dec 2022
B41G+731 Dec 2022
B51G+731 Dec 2022
B61G+731 Dec 2022
C71G+731 Dec 2022
C81G+731 Dec 2022
C91G+731 Dec 2022
D21G+731 Dec 2022
D31G+731 Dec 2022
D41G+731 Dec 2022
D51G+731 Dec 2022
D61G+731 Dec 2022
A11G+631 Dec 2022
A21G+631 Dec 2022

Legal and disputes

What disputes are disclosed?

16 complaints are on the MahaRERA record for KARRM PANCHTATVA-3, with orders passed in 16 of them.

16complaints

16with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005772127/05/2019FEHMIDA KAZI vs Karrm Infrastucture Pvt Ltdorder passed
CC00600000019402917/09/2020Jagdishbhai Maganlal Devmurari vs M/s Karrm Infrastructure Pvt. Ltd.order passed
CC00600000019625412/03/2021Anil Krishna Divekar vs Karrm Infrastructure Pvt. Ltdorder passed
CC00600000019662412/04/2021Nilesh Telgote vs Karrm Infrastructure Pvt. Ltdorder passed
CC00600000019663025/04/2021Mrs. Shanti Santosh Narvekar vs M/s. Karrm Infrastucture Pvt. Ltdorder passed
CC00600000019669212/06/2021Suchita Sunil Shirsat vs M/s. Karrm Infrastucture Pvt. Ltdorder passed
CC00600000019682703/05/2021Mr Kailash Harishchandra Ghag vs M/s. Karrm Infrastucture Pvt. Ltdorder passed
CC00600000019761519/07/2021Mrs. Rashmi Agrawal vs KARRM INFRASTRUCTURE PVT. LTD.order passed
CC00600000019749010/07/2021MRS NEHA MANISH SRIVASTAV vs KARRM INFRASTRUCTURE PVT LTDorder passed
CC00600000030359628/12/2022Vinayak Ramchandra Tari vs Karrm Infrastructure Private Limitedorder passed
CC00600000039646513/11/2023Megha Sajit Kumar vs Karrm Infrastructure Pvt. Ltd.order passed
CC00600000047982928/03/2024Sumeet Harold Nigli vs KARRM INFRASTRUCTURE PVT LTDorder passed
CC00600000048038306/05/2024THOMAS JOSEPH CHIRIYANKANDATH vs KARRM INFRASTRUCTURE PVT LTDorder passed
CC1240070307/11/2024Rajesh Shivmurat Vishwakarma vs KARRM INFRASTRUCTURE PRIVATE LIMITEDorder passed
CC1240084722/11/2024Ganesh Balwan Valanj vs KARRM INFRASTRUCTURE PRIVATE LIMITEDorder passed
CC1250016318/01/2025Debra Bosco Martin vs KARRM INFRASTRUCTURE PRIVATE LIMITEDorder passed

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 421601. Per the filed land record, the plot is bounded to the north by G NO 32 56, to the south by G NO 1038 10099, to the east by G NO 92 95 98 100 101 and to the west by G NO 48 53 54 107B. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 64 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park64 km
Andheri MIDC / SEEPZ66 km
Chhatrapati Shivaji Int'l Airport69 km
Bandra Kurla Complex (BKC)70 km
Lower Parel / Worli business district78 km
Nariman Point / Fort84 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Karrm Infrastructure Private Limited project & its RERA track record →

Other RERA-registered projects in Shahapur

Krishna Crown
declared completion Oct 2026 · Shree Krishna Reality
Sava Arcade
declared completion Oct 2026 · Sava Developers
Shantaram Park Residency
declared completion Dec 2026 · Shubha Developers
Darshan Ganesh Apartment
declared completion Dec 2026 · Tirupati Construction
Chintamani Meadows
declared completion Dec 2026 · Jashnani Construction Private Limited
Dreamland Park Building No.1
declared completion Dec 2026 · Kulswamini Builders AND Developers
More builders in Shahapur

Major developers building in Shahapur

More projects in Thane

Other RERA-registered projects in Thane

Karrm Residency -4
declared completion Nov 2020 · Karrm Infrastructure Private Limited
Karthik Heights
declared completion Jan 2025 · Ganesh Enterprises
Kartik Enclave
declared completion Dec 2029 · Shivaay Developers
Kartik Ganesh
declared completion Dec 2026 · JAI Mata JI Developers
Kartik Homes
declared completion Dec 2026 · Kartik Enterprises
Kartik Regency B Wing
declared completion Dec 2029 · Hi Tech Realtors

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.