Mumbai/Project record

MahaRERA · the public record

Kripa Prasad Co-operative Housing Society Limited

Mumbai Suburban · Haritara Construction Company

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Kripa Prasad Co-operative Housing Society Limited

MahaRERA · P51800003614

Delivery and registration

When is the project declared for completion?

Kripa Prasad Co-operative Housing Society Limited is registered with MahaRERA as P51800003614 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

28months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800003614
Registered on06 Aug 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Kripa Prasad Co-operative Housing Society Limited record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

Haritara Construction Company is the promoter of record on 4 projects registered with MahaRERA.

4projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Kripa Prasad Co-operative Housing Society Limited in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Kripa Prasad Co-operative Housing Society Limited1G+830 Jun 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Filed descriptions (status fields empty): 1 “suit and interim application pending”. These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court At Bombay Borivali Division At Dindoshi Goregaon942016Status not supplied
Filed description: suit and interim application pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 20201) As DCPR 2034 coming into force due to which there is not clarity as regards Reg. No. 14(A) for Amenities and Facility, Reg. No.15 for inclusive Housing and due to projection not
31 Dec 202030 Jun 2022Due to Covid-19 pandemic situation, shortage of labours & materials, we could not complete the construction work on time. So, we have received 75% consents from the Allottee/s to g
30 Jun 202230 Jun 2024After COVID 19 Pandemic situation, we, the Promoter were facing various financial difficulties. During the last RERA Certificate extension period i.e. till June 2022, the proposed

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400068. Per the filed land record, the plot is bounded to the north by Damodar Mhatre Road, to the south by CTS no 728 and CTS no 729, to the east by CTS No 720 Municipal Hospital and CTS no 721 and to the west by CTS no 723 Pitru Chhaya CHSL. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 15 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ15 km
Powai / Hiranandani business park17 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)22 km
Lower Parel / Worli business district29 km
Nariman Point / Fort37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dahisar East

Jeandveekedarnath
declared completion Dec 2026 · JE AND VEE Infrastructure
Shri Upendra Chsl
declared completion Dec 2026 · Harshal Enterprises
Swayam Niketan
declared completion Dec 2026 · Jainam Associates
A And O Eminente
Not filing quarterly progress reports · declared completion Dec 2026 · Ashapura Housing Private Limited
Amber Heights
declared completion Dec 2026 · Ghanshyam Enterprises
Ashtha Sharon Dahisar West
declared completion Dec 2026 · Indo Build Enterprise
More builders in Dahisar East

Major developers building in Dahisar East

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Kripa VUE
declared completion Sep 2024 · Kripa Oneness Private Limited
Krishaang A Wing
declared completion Jul 2023 · Jaycee Homes Private Limited
Krishna
declared completion Dec 2025 · Not Available
Krishna Bhavan SRA Housing Co.op.hsg.sty.ltd
declared completion Dec 2019 · Ganesh Star Builders
Krishna Coniq
declared completion Dec 2030 · Skydome Realtors LLP
Krishna Curve
declared completion Dec 2023 · Krishna Minerals

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.