Mumbai/Project record

MahaRERA · the public record

MATHURA KUNJ

NANDORE · SANJAY SHIVNATH SHUKLA

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
01 Jul 2025declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for MATHURA KUNJ

MahaRERA · P99000017337

Delivery and registration

When is the project declared for completion?

MATHURA KUNJ is registered with MahaRERA as P99000017337 and the promoter has declared completion for 01 Jul 2025.

01 Jul 2025

declared completion

15months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000017337
Registered on07 Aug 2018
Promoter-declared completion01 Jul 2025
Current statusCertificate Signed
Against todayabout 15 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MATHURA KUNJ record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-07-01).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MATHURA KUNJ in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
TYPE B BUILDING NO 021G+323 Apr 2022
TYPE A BUILDING NO 021G+323 Apr 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered01 Jul 2025PROJECT COULD NOT STARTED DUE TO COVID

Location, Land & Connectivity

Located at NANDORE, NANDORE, Vasai, Palghar, 401404. Per the filed land record, the plot is bounded to the north by 358, to the south by 58, to the east by 41 and to the west by 44. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Palghar

Shiv Krupa
declared completion Oct 2026 · Shivaay Realty
V Square Arcade
declared completion Oct 2026 · V Square
Nisarg Shrushti Phase-2
declared completion Nov 2026 · Arvel Realtors
Aloha
declared completion Nov 2026 · SEA Crests Buildcon LLP
Paramount Enclave Phase -1
declared completion Nov 2026 · Kavita Realty Housing LLP
Solitaire Park
declared completion Nov 2026 · Park Solitaire Lifespaces LLP
More builders in Palghar

Major developers building in Palghar

More projects in Palghar

Other RERA-registered projects in Palghar

Mathura Kunj
declared completion Dec 2024 · Ankush Harsuparsad Dubey
Mathuradham
declared completion Dec 2027 · Riddhi Siddhi Realty
Matoshri Heights
declared completion Oct 2026 · Nagesh Hemant Patil
Matru Sagar CO OP Housing Society Limited
declared completion Dec 2027 · Royal IB Infrastructure Private Limited
Matruchhaya
declared completion Dec 2027 · Jivdani Krupa Builders AND Developers
Matruchhaya Heights
declared completion Dec 2026 · Matruchhaya Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.