MIG / LIG Ts CTS No 165 at Tagore Nagar, Vikhroli, E

Mumbai Suburban · MHADA

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2019declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for MIG / LIG Ts CTS No 165 at Tagore Nagar, Vikhroli, E

MahaRERA · P51800000100

Delivery and registration

When is the project declared for completion?

MIG / LIG Ts CTS No 165 at Tagore Nagar, Vikhroli, E is registered with MahaRERA as P51800000100 and the promoter has declared completion for 30 Jun 2019.

30 Jun 2019

declared completion

88months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800000100
Registered on02 Jul 2017
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 88 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MIG / LIG Ts CTS No 165 at Tagore Nagar, Vikhroli, E record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

MHADA is the promoter of record on 18 projects registered with MahaRERA.

18projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MIG / LIG Ts CTS No 165 at Tagore Nagar, Vikhroli, E in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Sarvodaya bldg1G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2019Now the MHADA is declared as Special Planning Authority, the request for releasing O.C. for the same is made.

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400079. Per the filed land record, the plot is bounded to the north by GARDEN, to the south by CHAWL NO 286, to the east by D P ROAD and to the west by CHAWL NO 271. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 3 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park3 km
Chhatrapati Shivaji Int'l Airport6 km
Andheri MIDC / SEEPZ7 km
Bandra Kurla Complex (BKC)7 km
Lower Parel / Worli business district15 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Mhada project & its RERA track record →

Other RERA-registered projects in Vikhroli

THE X Ghatkopar
declared completion Dec 2026 · Arihant Realtors
Manthan Acropolis
declared completion Dec 2026 · Manthan Development Corporation
Aikya Roots
declared completion Jun 2027 · Racek Industries PVT LTD
Metro Crown
declared completion Dec 2027 · Metro Enterprises
Metro Crown Commercial
declared completion Dec 2027 · Metro Enterprises
Lodha Vikhroli-Signet
declared completion Jun 2028 · Lodha Developers Limited
More builders in Vikhroli

Major developers building in Vikhroli

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Milan Aura
declared completion Dec 2027 · Milan Interbuilt Private Limited
Milan Mandir NX
declared completion Mar 2027 · Milan Life Spaces LLP
Milan Milap CO OP Housing Society LTD
declared completion Dec 2026 · Milan Milap CO OP Housing Society Limite
Milestone
declared completion Dec 2029 · Gauri Developers
Milestone
declared completion Apr 2028 · Ojas Corporation
Minal AND Madhavkunj
declared completion Dec 2026 · Sevenfolds Constructions LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.