Mumbai/Project record

MahaRERA · the public record

NAMO SHIVAASTHU CITY BUILDING NO 3

Prabhadevi · SRK REAL HEIGHTS PRIVATE LIMITED

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
04 Feb 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for NAMO SHIVAASTHU CITY BUILDING NO 3

MahaRERA · P51900010075

Delivery and registration

When is the project declared for completion?

NAMO SHIVAASTHU CITY BUILDING NO 3 is registered with MahaRERA as P51900010075 and the promoter has declared completion for 04 Feb 2023.

04 Feb 2023

declared completion

44months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51900010075
Registered on23 Aug 2017
Promoter-declared completion04 Feb 2023
Current statusCertificate Signed
Against todayabout 44 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NAMO SHIVAASTHU CITY BUILDING NO 3 record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

SRK REAL HEIGHTS PRIVATE LIMITED is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NAMO SHIVAASTHU CITY BUILDING NO 3 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
BUILDING NO 31G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Prabhadevi, Off Veer Savarkar Road, Ward GSouth, Mumbai City, 400025. Per the filed land record, the plot is bounded to the north by SURVEY NO 130 B, to the south by EXISTING 6 M WIDE NALLA, to the east by 24 M WIDE D P ROAD and to the west by EXISTING 15 M WIDE ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 64 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ64 km
Powai / Hiranandani business park66 km
Chhatrapati Shivaji Int'l Airport69 km
Bandra Kurla Complex (BKC)71 km
Lower Parel / Worli business district79 km
Nariman Point / Fort87 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Prabhadevi

25 South Tower A 11th To 47th Floor
declared completion Dec 2026 · Twenty Five South Realty Limited
25 South Tower A Upto 10th Floor
declared completion Dec 2026 · Twenty Five South Realty Limited
25 South - Central Tower
Deregistered by MahaRERA · declared completion Dec 2028 · Twenty Five South Realty Limited
Kshitij Omkar
declared completion Nov 2030 · Omkar CHS Ltd
Vakratunda Crest
declared completion Dec 2030 · Inclineestate Properties LLP
Naia
declared completion Dec 2030 · Prabhadevi Developer Private Limited
More builders in Prabhadevi

Major developers building in Prabhadevi

More projects in Mumbai City

Other RERA-registered projects in Mumbai City

Namo Shivaasthu City Building NO 4
declared completion Feb 2024 · SRK Real Heights Private Limited
Namo Shivaasthu City Building NO 5
declared completion Feb 2024 · SRK Real Heights Private Limited
Nathani Heights Sale
declared completion Dec 2026 · Nathani Parekh Constructions Private Lim
Nathani Residency
declared completion Dec 2026 · Nathani Parekh Constructions Private Lim
Nathani Square
declared completion Dec 2026 · A.patni Realty Private Limited
Navkar Omnia
declared completion Dec 2027 · R V Property Ventures LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.