Mumbai/Project record

MahaRERA · the public record

Rite Luxuria

Mumbai Suburban · Rite Developers Pvt. Ltd.

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2019declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Rite Luxuria

MahaRERA · P51800006260

Delivery and registration

When is the project declared for completion?

Rite Luxuria is registered with MahaRERA as P51800006260 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

82months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800006260
Registered on14 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 82 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Rite Luxuria record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.

Promoter record

What else is this promoter on record for?

Rite Developers Pvt. Ltd. is the promoter of record on 10 projects registered with MahaRERA.

10projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Rite Luxuria in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
Rite Luxuria1G+1731 Dec 2019

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Rite Luxuria, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000008999308/07/2019SACHIN DASHRATH CHORGE vs RITE DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000019484902/02/2021PANKAJ MOHAN DALVI vs RITE DEVELOPERS PRIVATE LIMITEDorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019As per approved amended plan we had obtained full Commencement Certificate vide dated 30th August, 2018 as per certificate dated 8th October, 2018 from Ravi N. Gohil Architect, the

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400081. Per the filed land record, the plot is bounded to the north by CTS NO 554-1 492B 557-1, to the south by CTS NO 577 572 and 577, to the east by CTS NO 561 and to the west by CTS NO 560-B 557-2 578. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 8 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ11 km
Chhatrapati Shivaji Int'l Airport14 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district24 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Rite Developers Pvt. Ltd. project & its RERA track record →

Other RERA-registered projects in Mulund East

Mithagar Road Ekta Chsl
declared completion Dec 2026 · Palan Realty Private Limited
Bimal Apartment Chsl
declared completion Dec 2026 · Rite Builders & Developers
Govind Prakash SRA CHS LTD
declared completion Dec 2026 · Omsai Developers
Jvms Monica Gardens
declared completion Dec 2026 · JVM Spaces
Mahatma Jyotiba Phule CHS LTD
declared completion Dec 2026 · Tridevh Construction Company
OM Mayuresh
declared completion Dec 2026 · M/s Keytech
More builders in Mulund East

Major developers building in Mulund East

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Rite Nectar Phase II
declared completion Sep 2022 · Rite Developers Pvt. Ltd.
Rite Oscar
declared completion Jun 2021 · Rite Properties
Rite Perinto
declared completion Mar 2022 · Rite Developers Pvt. Ltd.
Rite Prime
declared completion Dec 2017 · Rite Developers Pvt. Ltd.
Rite Skyluxe
declared completion Dec 2021 · Rite Developers Pvt. Ltd.
Rivaan
declared completion Dec 2028 · M/s Meghna Infracon LLP

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.