SAHARA ELITE

AMBARNATH, THANE · SAHARA ELITE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

8units filed as unsoldInventory · 12 September 2026
29 May 2024declared completionMahaRERA registration · read 12 Jul 2026
62registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 May 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700032478

Delivery and registration

When is the project declared for completion?

SAHARA ELITE is registered with MahaRERA as P51700032478 and the promoter has declared completion for 29 May 2024.

29 May 2024

declared completion

28months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700032478
Registered on04 Jan 2022
Promoter-declared completion29 May 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAHARA ELITE record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sahara Elite is the promoter of record on 29 projects registered with MahaRERA, 7 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

29projects

registered with MahaRERA

7flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In SAHARA ELITE, 54 of 62 homes filed with MahaRERA are recorded as sold or booked (53 with registered agreements and 1 booked), about 87%, and 8 remain available.

87%sold

54 of 62 homes

₹20.75 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹20.75 Cr (about 100%) is recorded as collected and ₹0 as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 54 registered agreements, the effective carpet rate is ₹9,273/sqft, with eight in ten falling between ₹928 and ₹11,022 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1102288 sqft (26.77 sqm)₹16.44 Lakh
Floor 7702288 sqft (26.77 sqm)₹16.44 Lakh
Ground/Floor 0101119 sqft (11.09 sqm)₹21.36 Lakh
Ground/Floor 0201122 sqft (11.29 sqm)₹21.36 Lakh
Ground/Floor 0301168 sqft (15.61 sqm)₹21.36 Lakh
Ground/Floor 0401168 sqft (15.61 sqm)₹21.36 Lakh
Ground/Floor 0501122 sqft (11.29 sqm)₹21.36 Lakh
Ground/Floor 0601119 sqft (11.09 sqm)₹21.36 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 12 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 54 homes carry one, and 8 of the 62 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
102288 sqftRs 29.17 lakh typical, over Rs 24.03 lakh to Rs 2.8147 cr5 filed on this stack, floors 2–6

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In SAHARA ELITE, 2 of the 8 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 7 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 62 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SAHARA ELITE1G+762-

Unit mix on the filing: 56 residential and 6 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 May 2024DUE TO REVISED PLANS WE HAVE TO EXTEND OUR DATE FOR 12 MONTHS

Location, Land & Connectivity

Located at AMBARNATH, THANE, CHEROBA CHOWK, Kalyan, Thane, 421306. Per the filed land record, the plot is bounded to the north by OPEN PLOT S NO 3 14 9, to the south by OPEN PLOT S NO 3 14 7, to the east by OPEN PLOT and to the west by NAMDEV DHAM. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kalyan East

Kohinoor Eden
possession by Sep 2026 · KGI Realty Private Limited
Kohinoor Eden Ph 2
possession by Sep 2026 · KGI Realty Private Limited
Krishna Glory
possession by Oct 2026 · Tulsi Kimaya Construction
Trimurti Garden
possession by Dec 2026 · SAI Narayan Developers
Rai S Aaragya
possession by Dec 2026 · RAI Residency Private Limited
Rai S Heaven
possession by Dec 2026 · RAI Residency Private Limited

Major developers building in Kalyan East

Other RERA-registered projects in Thane

Sahara Residency
declared completion Jun 2025 · Sahara Residency
Sahyadri Elite
possession by Mar 2028 · Sikeria Shelter Private Limited
Sahyadri Residency Phase I
declared completion Dec 2023 · M/S Nirman Developers
Sahyadri Villas
declared completion Nov 2019 · Ashoka Dreams Developers
Sahyog IBM
declared completion Dec 2024 · S S Construction
SAI Aashiyana - II
declared completion Jun 2026 · Sai Sakshi Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 14 Sep 2026