Sai Arcade

PHADKE ROAD DOMBIVLI EAST · Sai Mangal Enterprises

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Sep 2025declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Sai Arcade

MahaRERA · P51700003993

Delivery and registration

When is the project declared for completion?

Sai Arcade is registered with MahaRERA as P51700003993 and the promoter has declared completion for 30 Sep 2025.

30 Sep 2025

declared completion

13months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700003993
Registered on07 Aug 2017
Promoter-declared completion30 Sep 2025
Current statusCertificate Signed
Against todayabout 13 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sai Arcade record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sai Arcade in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
A Wing1G+1031 Dec 2020
WING B1G+1431 Dec 2020
Proposed not sanctioned1--

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Sai Arcade, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000022082815/04/2022malhar darshan society vs SAI MANGAL ENTERPRISESorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2022THERE IS A MATERAIL SHORTAGE SIMULTENEOUSLY LABOUR ALSO SHORTAGE DUE TO PANDEMIC CITUALTION OF COVID 19 PROKJECT WORK IS SLOW DUE TO MAIN REASON PROJECT IS NOT YET COMPLTED WE NEED
30 Dec 202231 Mar 2024a
31 Mar 202430 Sep 2025SHORTAGE OF MATERIAL AND LABOUR

Location, Land & Connectivity

Located at PHADKE ROAD DOMBIVLI EAST, GANPATI MANDIR CROSS ROAD , Kalyan, Thane, 421201. Per the filed land record, the plot is bounded to the north by HARI CHAYA CHS, to the south by 15 MTR D P ROAD, to the east by SHREE JALARAM ASHISH SOCIETY and to the west by DEDHIA NIWAS CHS. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 27 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park27 km
Andheri MIDC / SEEPZ30 km
Chhatrapati Shivaji Int'l Airport32 km
Bandra Kurla Complex (BKC)33 km
Lower Parel / Worli business district41 km
Nariman Point / Fort47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivli East

Shanu Majestic
declared completion Dec 2026 · Fortune Group Of Construction
Balaji Annex
declared completion Dec 2026 · M/S OM Swayambhu Siddhivinayak Builders
Leela Shankar Residency
declared completion Dec 2026 · Ekveera AAI Construction
Ram Janaki
declared completion Dec 2026 · Shree Ganesh Enterprises
UMA Lambodar Heights
Not filing quarterly progress reports · declared completion Dec 2026 · Shree RAJ Properties Developers
Aditya Heights
declared completion Dec 2026 · Ashapura Developers
More builders in Dombivli East

Major developers building in Dombivli East

More projects in Thane

Other RERA-registered projects in Thane

SAI Arcade
declared completion Dec 2027 · Ganesh Developers
SAI Arcade
declared completion Dec 2028 · SAI Siddhi Enterprises
SAI Avenue
declared completion Jan 2025 · SAI Baba Constructions
Sai Baliram
declared completion Dec 2027 · Annapurna Infra
SAI Builders AND Developers
declared completion Feb 2025 · Shivsagar Gurucharan Yadav
SAI Castle
declared completion Dec 2028 · Pinnakle Lifespaces LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.