Mumbai/Project record

MahaRERA · the public record

SAMRUDDHI ENCLAVE

Alibag · SAMRUDDHI ENTERPRISES

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for SAMRUDDHI ENCLAVE

MahaRERA · P52000021710

Delivery and registration

When is the project declared for completion?

SAMRUDDHI ENCLAVE is registered with MahaRERA as P52000021710 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

28months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52000021710
Registered on19 Jul 2019
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAMRUDDHI ENCLAVE record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

SAMRUDDHI ENTERPRISES is the promoter of record on 4 projects registered with MahaRERA.

4projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAMRUDDHI ENCLAVE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
SAMRUDDHI ENLCAVE1G+530 Jun 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2023SINCE INCEPTION OF THE PROJECT WE ARE FACING THE ISSUE OF COVID - 19 PANDEMIC AND CONSEQUEST NATION-WIDE LOCKDOWN WITH EFFECT FROM MARCH 2020, REVERSE MIGRATION OF LABOUR AND BREAK
30 Jun 202330 Jun 2024As we have received the long awated permissions, our work which was getting delayed is now being boosted. Hence we need time to complete the delayed construction with the consent o

Location, Land & Connectivity

Located at Alibag, Alibag, Andheri, Mumbai Suburban, 402201. Per the filed land record, the plot is bounded to the north by ROAD, to the south by OPEN PLOT, to the east by PLOT NO 11 AND 12 and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Alibag

Excellensea Villas Project
declared completion Dec 2026 · Unicorp Realty Private Limited
Balibaug Rekreasi
declared completion Dec 2026 · Pushpam Infra LLP
Lakshminarayan CO-OP Housing Society LTD Proposed
declared completion Dec 2026 · Elnube Realtors PVT LTD
Swastik Orchid
declared completion Dec 2026 · Swastik Developers
Savitri Heritage
declared completion Mar 2027 · Mukesh Bhoormal Jain
Shree Radha Krishna Residency
declared completion May 2027 · Shree Radha Enterprises
More builders in Alibag

Major developers building in Alibag

More projects in Raigarh

Other RERA-registered projects in Raigarh

Samruddhi Green View
declared completion Dec 2030 · Ajinkya Tushar More
Sandhya Sadan
declared completion Dec 2026 · Sujit Janardhan Mhatre
Sankalp Meadows
declared completion Jun 2025 · NEW Path Developers LLP
Sansaaraa
declared completion Jun 2028 · SAI Darshan
Sanskruti
declared completion Sep 2026 · Sandip Shankar Patil
Sanskruti Plots, Phase III
declared completion Dec 2018 · Shreekant And Sachin Chopda

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.