SARTH APARTMENT BUILDING NO 2 PHASE I

KARJAT · Y S Patil Builders and Developers

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

46units filed as unsoldInventory · 22 October 2026
31 Dec 2028declared completionMahaRERA registration · read 18 Jul 2026
91registered unitsMahaRERA registration · read 18 Jul 2026

From another project · Empire Solitaire

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Empire Solitaire Project Review · first page
First page of the complete sample.

Free project details

Registration read 18 Jul 2026

RERA details for SARTH APARTMENT BUILDING NO 2 PHASE I

MahaRERA · P52000015029

Delivery and registration

When is the project declared for completion?

SARTH APARTMENT BUILDING NO 2 PHASE I is registered with MahaRERA as P52000015029 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

26months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52000015029
Registered on22 Jan 2018
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today26 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SARTH APARTMENT BUILDING NO 2 PHASE I record 4 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

  • Filing progress reports — 4 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In SARTH APARTMENT BUILDING NO 2 PHASE I, ₹4.50 Cr of a declared ₹5.50 Cr estimated project cost is reported as incurred, about 81.8%, as at the last certified filing with MahaRERA.

81.8%

₹4.50 Cr

of ₹5.50 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 18 Jul 2026

Sales

How many are filed as sold or booked?

In SARTH APARTMENT BUILDING NO 2 PHASE I, 37 of 91 homes filed with MahaRERA are recorded as sold or booked (36 with registered agreements and 1 booked), about 41%, and 54 are filed as unsold.

41%sold or booked

37 of 91 homes

₹4.82 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹4.35 Cr (about 90%) is recorded as collected and ₹47.22 Lakh as receivable.

Source · MahaRERA sold/unsold inventory filing · read 18 Jul 2026

Filed agreement values: across 37 sold or booked entries with usable filed values and areas, the effective carpet rate is ₹5,066/sqft, with eight in ten falling between ₹3,954 and ₹6,962 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 22 October 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific home. On this project 45 homes carry one, and 46 of the 91 are recorded unsold. Since we started watching this ledger, 8 homes have moved out of the unsold list, most recently on 08 September 2026.

Here is one home filed as unsold, beside the amounts filed for comparable homes:

HomeCarpetFiled comparisonBased on
A-1240 sqftRs 11.67 lakh typical, over Rs 6.25 lakh to Rs 17.25 lakh
1 unusually low or high filed amount is included in this range. Check the individual entries before using it to discuss a price.
26 filed · similar area (within 2%), elsewhere in project

A filed consideration is the amount the promoter reported for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In SARTH APARTMENT BUILDING NO 2 PHASE I, 39 of the 46 unsold homes have filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.

See the other 45 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 91 homes are registered across the project.

BuildingWingsFloorsUnitsDeclared completion
A WING1G+71831 Dec 2018
B WING1G+82831 Dec 2018
C WING1G+72831 Dec 2018
D WING1G+71731 Dec 2018

Unit mix on the filing: 91 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2022Major inventory is Unsold.
30 Dec 202230 Dec 2022Due to the market issue the booking of the properties no done as we expected. Therefore we don't have enough fund to complete the project as we mentioned at the time of registratio
30 Dec 202231 Dec 2025Project was delayed because of slow market transaction and consumer expectation about their home/house/flat, also there is competition in market about construction works. Also, the
31 Dec 202531 Dec 2028• Financial and Material/Labour Shortages: Ongoing challenges with rising material costs and a shortage of skilled labour have made it difficult to meet the original construction d

Location, Land & Connectivity

Located at KARJAT, KARJAT, Panvel, Raigarh, 410201. Per the filed land record, the plot is bounded to the north by NALA, to the south by SURVEY NO 23, to the east by GRAMMAPANCHAYAT ROAD and to the west by SURVEY NO 22. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 52 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park52 km
Bandra Kurla Complex (BKC)53 km
Chhatrapati Shivaji Int'l Airport54 km
Nariman Point / Fort54 km
Lower Parel / Worli business district55 km
Andheri MIDC / SEEPZ55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Karjat

Warai Woods Ph 2
Not filing quarterly progress reports · declared completion Nov 2026 · Nahar Riddhi Siddhi Developers
Jambrung Valley
declared completion Nov 2026 · Kirtiraj Nanasaheb Sawant
Bliss Studio
declared completion Dec 2026 · Balsam Builders
Beverly Hills
declared completion Dec 2026 · Rudram Infra Projects Private Limited
Jupiter Heights
Not filing quarterly progress reports · declared completion Dec 2026 · Jupiter Heights
Adwait
Not filing quarterly progress reports · declared completion Dec 2026 · Venkatesh Developers
More builders in Karjat

Major developers building in Karjat

More projects in Raigarh

Other RERA-registered projects in Raigarh

Sarthk Complex
declared completion Dec 2028 · Ashvamegh Realtors & Developers Priv
Sarvam
declared completion Dec 2026 · Ashtvinayak Homes
Sarvamangala Residency
declared completion Dec 2029 · OM SAI Homes Builders
Sarvoday Nagar
declared completion Jan 2029 · Bhavi Enterprises
Sathe Sukrut
declared completion Dec 2030 · Ace Realtors
Satya Govind
declared completion Jun 2026 · Sunil Mohandas Makhija

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.