Mumbai/Project record

MahaRERA · the public record

Suki-Nihon-Phase 2

Bamangaon, Bagmala · NIMESH KIRTI CHHATBAR

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2027declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for Suki-Nihon-Phase 2

MahaRERA · P52000047618

Delivery and registration

When is the project declared for completion?

Suki-Nihon-Phase 2 is registered with MahaRERA as P52000047618 and the promoter has declared completion for 30 Jun 2027.

30 Jun 2027

declared completion

8months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP52000047618
Registered on14 Nov 2022
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today8 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Suki-Nihon-Phase 2 record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 19 Jul 2026

View the free 14-item checklist →

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Promoter record

What else is this promoter on record for?

NIMESH KIRTI CHHATBAR is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 19 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Suki-Nihon-Phase 2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
Type A1G+131 Dec 2024
Type A1G+131 Dec 2024
Type A1G+131 Dec 2024
Type B1G+231 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2027We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, c

Location, Land & Connectivity

Located at Bamangaon, Bagmala, Mandve, Thane, Thane, 402204. Per the filed land record, the plot is bounded to the north by HARISHCHANDRA LAXMAN PATIL, to the south by WELL, to the east by JAYWANT KASHINATH NAIK and to the west by MORESHWAR NANA GHARAT. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nagaon

Nilaya
declared completion Dec 2026 · Fourthstreet Consultancy LLP
Coral Bay
declared completion Dec 2028 · Dynamix Vacation Resorts Private Limited
Coral Court
declared completion Dec 2028 · Dynamix Vacation Resorts Private Limited
Coral Nest
declared completion Dec 2028 · Dynamix Vacation Resorts Private Limited
Creata Harmony
declared completion Dec 2028 · Creata Lifespaces Llp
Cidade Vida
declared completion Dec 2029 · Bhide Lifespaces
More builders in Nagaon

Major developers building in Nagaon

More projects in Raigarh

Other RERA-registered projects in Raigarh

Sukoon
declared completion Dec 2028 · Greensspaces
Sukoon Empire Bldg A AND B
declared completion Apr 2030 · Sukoon Homes Builders AND Developers
Sukoon Residency
declared completion Jun 2027 · Rifaa Structural Solutions Private Limit
Suman Residency
declared completion Dec 2024 · Pranay Kanha Koli
Sumati Paradise
declared completion May 2024 · Mahendra Tambaram Patel
Summer Hills
declared completion Jun 2028 · Asfak Sharakat Choudhari

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.