THE HEIGHTS

Marol · DHRUVI PROPERTIES PVT LTD

Is this the right project?
Which unit should you choose?

Read the free RERA facts below. For help choosing a unit or comparing a price, select a report.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2026declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for THE HEIGHTS

MahaRERA · P51800007232

Delivery and registration

When is the project declared for completion?

THE HEIGHTS is registered with MahaRERA as P51800007232 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

2months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800007232
Registered on17 Aug 2017
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today2 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for THE HEIGHTS record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for THE HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
EMPRES HEIGHTS B1G+1131 Dec 2024
EMPRESS HEIGHTS A1G+1031 Dec 2024

Legal and disputes

What disputes are disclosed?

7 complaints are on the MahaRERA record for THE HEIGHTS, with orders passed in 6 of them.

7complaints

6with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000002332822/02/2018Pradeep Nair vs KSL & Industries Ltd and Othersorder passed
CC00600000005580216/08/2018ANITA SHETTY vs DHRUVI PROPERTIES PVT. LTD.order passed
CC00600000005685509/11/2018Patrick Almeida vs Dhruvi Properties Pvt Ltdorder passed
CC00600000010039205/08/2019M/S. DHRUVI PROPERTIES PVT LTD vs M/s. Dhruvi Properties Pvt. Ltd.order passed
CC00600000010042405/08/2019HENRY JOSEPH vs M/s. Dhruvi Properties Pvt. Ltd.order passed
CC00600000019568518/01/2021Samuel Rathnakar Andrews vs KSL & Industries Ltdorder passed
CC00600000019867914/10/2021Mr Sudhir Hegde & Mrs Lalita Carolena Misquitta vs KSL & Industries Ltdpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022Due to shortage of labours and contractor because of COVID the work is not able to complete on time. 90% of the work is done therefore we need an extention of period to be able to
30 Jun 202231 Dec 2024THE PROJECT IS COMPLETED IN ALL ASPECTS BUT THE MAIN COMPANY THAT IS HOLDING THE RIGHTS TO THE PLOT (IE KSL & INDUSTRIES LTD) PROMOTER IN CURRENTLY IN NCLT AND UNDER MONITORIUM THE
31 Dec 202431 Dec 2026Due to material shortages, labor shortages, and insufficient funding, the construction work for the project is currently on hold. Additionally, the completion certificate is still

Location, Land & Connectivity

Located at Marol, Marol Maroshi road , Ward GSouth, Mumbai City, 400059. Per the filed land record, the plot is bounded to the north by NALA, to the south by DP ROAD, to the east by DP RD and to the west by DP ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 27 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park27 km
Bandra Kurla Complex (BKC)29 km
Chhatrapati Shivaji Int'l Airport30 km
Andheri MIDC / SEEPZ31 km
Lower Parel / Worli business district33 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri East

Royal Green
declared completion Dec 2026 · Admire Revive Builder & Developer
VKG Estates
declared completion Dec 2026 · Greenery Rock LLP
59 Avenue
declared completion Dec 2026 · M/s Ganesh Vishal Infra Engineering Priv
Gateway Residences
declared completion Dec 2026 · Infinity Narayani Associates
LA Grace
declared completion Dec 2026 · Ecohomes Ventures
Park Royale Phase III
declared completion Dec 2026 · Shivranjani Properties LLP
More builders in Andheri East

Major developers building in Andheri East

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

THE Kollage
declared completion Aug 2026 · Zire Rushi Construction
THE Konark Rise
declared completion Dec 2027 · Konark Rajendra Shah
THE Legend
declared completion Dec 2027 · Black Rock
THE Lisa
declared completion May 2025 · Shethwala Infra
THE Mansion
declared completion Sep 2028 · Not Available
THE Mariano
declared completion Jun 2022 · Pioneer Enterprises

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.