VARDHMAN GARDEN PHASE II

BALKUM · DIWALI CONSTRUCTION COMPANY

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for VARDHMAN GARDEN PHASE II

MahaRERA · P51700018761

Delivery and registration

When is the project declared for completion?

VARDHMAN GARDEN PHASE II is registered with MahaRERA as P51700018761 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700018761
Registered on04 Dec 2018
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VARDHMAN GARDEN PHASE II record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

DIWALI CONSTRUCTION COMPANY is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VARDHMAN GARDEN PHASE II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
LAVENDER WING A1G+331 Dec 2020
LAVENDER WING B1G+2231 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 20231. Approvals could not be availed due to the changes in guidelines and procedures. 2. To process further technical requirements and approvals from TMC. 3. Due to unavailability o

Location, Land & Connectivity

Located at BALKUM, BALKUM ROAD, Ward ABCD, Mumbai City, 400608. Per the filed land record, the plot is bounded to the north by BMC PIPELINE, to the south by MUMBAI AGRA ROAD, to the east by ARYA CENTRE and to the west by D P ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 14 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ16 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)21 km
Lower Parel / Worli business district30 km
Nariman Point / Fort37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Balkum

Dosti West County - Dosti Tulip
declared completion Oct 2026 · Dosti Enterprises
Highland Springs B4 D Wing
declared completion Dec 2026 · Siddhi Real Estate Developers
Mahavir Bliss
declared completion Dec 2026 · M/s. Shivshakti Engineers
Shraddha Peninsula
declared completion Dec 2026 · Padmagriha Heights
Sumeet Elite
declared completion May 2027 · Vedant Construction
Dosti West County - Dosti Nest - Phase 1
declared completion Jun 2027 · Dosti Enterprises
More builders in Balkum

Major developers building in Balkum

More projects in Thane

Other RERA-registered projects in Thane

Varhaala Heights
declared completion Mar 2028 · Sarvashiva Enterprises
Varsha Co-Operative Housing Society Limited
declared completion Dec 2030 · JE Developer & Contractors
Varun Apartment
declared completion Dec 2022 · V N Developers
Varun Enclave
declared completion Dec 2028 · Not Available
Varun Heritage
declared completion Dec 2025 · Waman Barku Mhatre
Varun Hillcrest
declared completion Dec 2027 · Not Available

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.