Mumbai/Project record

MahaRERA · the public record

VICTORY HEIGHTS

BORIVALI · VJAY VICTORY REALTORS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
01 Sep 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for VICTORY HEIGHTS

MahaRERA · P51800009567

Delivery and registration

When is the project declared for completion?

VICTORY HEIGHTS is registered with MahaRERA as P51800009567 and the promoter has declared completion for 01 Sep 2022.

01 Sep 2022

declared completion

49months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800009567
Registered on22 Aug 2017
Promoter-declared completion01 Sep 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VICTORY HEIGHTS record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VICTORY HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
VICTORY HEIGHTS A AND B WING1G+1331 Dec 2018

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for VICTORY HEIGHTS, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000029268117/09/2022Diwaliben P Ravariya vs Vjay Victory Realtorsorder passed
CC00600000039608109/06/2023Jileshl J Lakhani vs HIMANSHU NARENDRA SHAHorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019Delay in Getting the necessary permission such as IOD Copy & Commencement Certificate for Upper 9 Floor (Pt.) till upper 12th floor
31 Dec 201931 Mar 2021DUE TO DELAY IN GETTING PERMISSION FROM COMPETENT AUTHORITY THE PROJECT WAS UNABLE TO GET COMPLETED ON TIME, THEREFORE WE WOULD REQUEST YOU TO PLEASE GRANT US EXTENSION U/S 7(3) FO
31 Mar 202101 Mar 2022We have been seeking for the extension as due to COVID 19 Pandemic the project was completely Stopped and hence we are seeking for the extension of the project till June 2022

Location, Land & Connectivity

Located at BORIVALI, BORIVALI, Borivali, Mumbai Suburban, 400092. Per the filed land record, the plot is bounded to the north by SOCIAL FACILITY PLOT, to the south by 18 MTS PLOT RDPI, to the east by NALLA AND 100 SQ MT PLOTS and to the west by HIG PLOT 33 AND HEALTH CARE CENTRE. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 12 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park15 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district26 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali West

Navkar Palazzo
Not filing quarterly progress reports · declared completion Dec 2026 · Navkar Infra Projects
THE Zone
declared completion Dec 2026 · MS Amann RAJ Housing AND Development Cor
9 Rajgir
declared completion Dec 2026 · M S Kavita Construction Company
Adarsh Garden Grove
declared completion Dec 2026 · Adarsh Enterprises
Akshaya AND Jayshree Redevelopment
declared completion Dec 2026 · NHI Developers LLP
Atulya
declared completion Dec 2026 · Phoenix Developers
More builders in Borivali West

Major developers building in Borivali West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Victory Platinum
declared completion Dec 2019 · Prashanti Land Developers Private Limite
Victory Stella Nestle
declared completion Jun 2028 · Victory Venture Developers
Vida Stellaris
declared completion Dec 2030 · Prima Terra Estates Private Limited
Vidya Nidhi
declared completion Mar 2024 · Laxmi Aakar Realty
Vidyalankar Chsl
declared completion Jul 2026 · Desai Residency Private Limited
Vighnaharta
declared completion Mar 2024 · Ajit Sakharam Chavan

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.