VINAYAK SHRADDHA TOWER

BANDRA EAST · K K KRISHNAN CONSTRUCTION COMPANY PVT LTD

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2025declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for VINAYAK SHRADDHA TOWER

MahaRERA · P51800003341

Delivery and registration

When is the project declared for completion?

VINAYAK SHRADDHA TOWER is registered with MahaRERA as P51800003341 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

10months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800003341
Registered on05 Aug 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VINAYAK SHRADDHA TOWER record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Promoter record

What else is this promoter on record for?

K K KRISHNAN CONSTRUCTION COMPANY PVT LTD is the promoter of record on 4 projects registered with MahaRERA.

4projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VINAYAK SHRADDHA TOWER in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
INDIRAKRUPA1G+14-
VINAYAK SHRADDHA TOWER1G+16-
MUNICIPAL PRIMARY SCHOOL1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2024It is a redevelopment project. Due to pandemic, the financial condition to conduct the construction and fulfill the rentals to tenants and other expenses was not suitable, hence we
31 Dec 202431 Dec 2025We faced financial crisis during covid and were unable to raise funds, hence we introduced a co-promoter who agreed to fund the project construction. Our existing tenants of rehab

Location, Land & Connectivity

Located at BANDRA EAST , VIJAYNAGAR, Andheri, Mumbai Suburban, 400051. Per the filed land record, the plot is bounded to the north by SRA BUILDING, to the south by INTERNAL ROAD, to the east by SLUM and to the west by SRA UNDER CONSTRUCTION BLDG. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 2 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Bandra Kurla Complex (BKC)2 km
Chhatrapati Shivaji Int'l Airport4 km
Lower Parel / Worli business district7 km
Andheri MIDC / SEEPZ8 km
Powai / Hiranandani business park8 km
Nariman Point / Fort15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bandra East

A And O Estado
Not filing quarterly progress reports · declared completion Dec 2026 · Ashapura Builders AND Developers
Antariksh Ace
declared completion Dec 2026 · Pittie Antariksh Realty Private Limited
Bandra North Gulmohar Avenue
declared completion Dec 2026 · Shivalik Ventures Private Limited
Gurukrupa Nirmalam
declared completion Dec 2026 · Gurukrupa Realcon Infrastructure LLP
LEO Eminence
declared completion Dec 2026 · LEO Infrastructure Private Limited
Mayur Tower
declared completion Dec 2026 · Geopreneur Spire Realty
More builders in Bandra East

Major developers building in Bandra East

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Vindhyagiri
declared completion Dec 2025 · Gio Properties
Vintage
declared completion Dec 2023 · Vora Estates
Vir Enclave
declared completion Jun 2025 · JKD Engineers AND Infrastructure Private
VIR Paradise
declared completion Nov 2027 · JKD Engineers AND Infrastructure Private
Vira Avenue
declared completion Dec 2026 · Vira Realty India Private Limited
Vira ONE
declared completion Dec 2026 · Grow More Builders AND Developers Privat

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.