GREEN VALLEY

Nagpur · Samiran Kayal

Is this the right project?
Which unit should you choose?

Read the free RERA facts below. For help choosing a unit or comparing a price, select a report.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

Free project details

Registration read 12 Jul 2026

RERA details for GREEN VALLEY

MahaRERA · P50500032876

Delivery and registration

When is the project declared for completion?

GREEN VALLEY is registered with MahaRERA as P50500032876 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

28months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP50500032876
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GREEN VALLEY record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Sales

How many are filed as sold or booked?

In GREEN VALLEY, 0 of 139 units filed with MahaRERA are recorded as sold or booked, about 0%, and 139 are filed as unsold.

0%sold or booked

0 of 139 units

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 05 Sep 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GREEN VALLEY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Location, Land & Connectivity

Located at Nagpur. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Hingna

Abhay Residency II
declared completion Dec 2026 · Modokar Infra Private Limited
Central Town
declared completion Dec 2026 · Agresar Infrastructure Through Proprieto
Chaitanya Vihar-2
declared completion Dec 2026 · Chaitanya Gruhanirman Sahakari Sanstha
DND SKY
declared completion Dec 2026 · DND Infrastructure
Green Gold
declared completion Dec 2026 · Dera Developers
Kanchan Nagari-3 Part
declared completion Dec 2026 · Shubh Infrastructure
More builders in Hingna

Major developers building in Hingna

More projects in Nagpur

Other RERA-registered projects in Nagpur

Green View Residency
declared completion Jan 2020 · N K Associates
Greencity 5
declared completion Dec 2029 · Open Door Realty
Greenfield 1 Wing D
declared completion Dec 2019 · L G Developers AND Builders
Greenfield 2
declared completion Mar 2024 · L G Developers AND Builders
Greenfield 3
declared completion Aug 2026 · L G Developers AND Builders
Greenfield 4
declared completion Aug 2027 · L G Developers AND Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Nagpur projects.

Registration last seen on RERA: 20 Oct 2026. Document and inventory dates are shown in their sections.