DHANLAXMI HEIGHTS

Pune · DHANLAXMI DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Oct 2019declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for DHANLAXMI HEIGHTS

MahaRERA · P52100012530

Delivery and registration

When is the project declared for completion?

DHANLAXMI HEIGHTS is registered with MahaRERA as P52100012530 and the promoter has declared completion for 31 Oct 2019.

31 Oct 2019

declared completion

84months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100012530
Registered on01 Sep 2017
Promoter-declared completion31 Oct 2019
Current statusCertificate Signed
Against todayabout 84 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DHANLAXMI HEIGHTS record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

DHANLAXMI DEVELOPERS is the promoter of record on 5 projects registered with MahaRERA.

5projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for DHANLAXMI HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
A1G+7-
B1G+7-
C1G+5-
D1G+5-
E1G+5-

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for DHANLAXMI HEIGHTS, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000001120927/03/2018Vijay Sacchidanand Khatavkar vs Dhanlaxmi Developersorder passed
CC00500000007517004/02/2021VIJAY SACCHIDANAND KHATAVKAR vs DHANLAXMI DEVELOPERSorder passed
CC00500000005401006/02/2020Ravindra Nanasaheb Kharde vs Dhanlaxmi Developersorder passed
CC00500000006496725/12/2020NILESH PURUSHOTTAM KHACHANE vs Shailesh Shantilal Patelorder passed
CC1250407319/11/2025RUPESH KANTILAL CHOPDA vs DHANLAXMI DEVELOPERSorder passed

Location, Land & Connectivity

Located at Haveli, Pune, 412105. Per the filed land record, the plot is bounded to the north by 923 P, to the south by 923 P53, to the east by GAT NO 918 and to the west by 6-12 M WIDE ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 14 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)10 km
Kharadi / EON IT Park14 km
Pune Junction / city centre16 km
Magarpatta / Hadapsar IT17 km
Baner–Balewadi belt19 km
Hinjewadi Rajiv Gandhi IT Park21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Moshi

Anantam Skyone
declared completion Oct 2026 · Rajshree Landmark LLP
Excel Celestia Residency E AND F AND Mhada
declared completion Oct 2026 · Excel Housing
Skyline Pride
declared completion Oct 2026 · Ajit Dnyaneshwar Pawar
THE Business Gate
declared completion Oct 2026 · Kesar Vasudev Properties
Stella B1
declared completion Nov 2026 · DMK Infrastructure PVT LTD
Clone Tiara
declared completion Nov 2026 · Clone Properties LLP
More builders in Moshi

Major developers building in Moshi

More projects in Pune

Other RERA-registered projects in Pune

Dhanlaxmi Market
declared completion Dec 2026 · Dhanlaxmi Infra
Dhanmai Aavaas
declared completion Mar 2022 · MS Rathi Construction Through ITS Propri
Dhanmai Complex
declared completion Dec 2019 · Ravindra Dhanraj Rathi
Dhanwantari Terrace Cooperative Housing Society Limited
declared completion Dec 2017 · Digamber Parulekar
Dhara Icon
declared completion Dec 2023 · D R Bhondve Properties
Dharampal Corporate Avenue
declared completion Dec 2026 · Surender Dharampal Agarwal

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.