KONIFER

Pune · KONBIL LANDMARKS LLP

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Jul 2023declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for KONIFER

MahaRERA · P52100022989

Delivery and registration

When is the project declared for completion?

KONIFER is registered with MahaRERA as P52100022989 and the promoter has declared completion for 31 Jul 2023.

31 Jul 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP52100022989
Registered on08 Nov 2019
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KONIFER in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
KONIFER1G+1031 Jul 2022

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for KONIFER, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 19 Jul 2026

Complaint no.FiledPartiesStatus
CC1250315407/09/2025Bharat Bhausaheb Takle vs KONBIL LANDMARKS LLPorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2023Due To Revision Plan, Increase & Additional Of Area.

Location, Land & Connectivity

Located at Pune, Mundhawa, Haveli, Pune, 411036. Per the filed land record, the plot is bounded to the north by By part of Survey No 89A-11D, to the south by By part of Survey No 89A-11E, to the east by By part of Survey No 90 and to the west by By part of Survey No 89A-10. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mundhwa

The Golden Bell
Not filing quarterly progress reports · declared completion Dec 2026 · Panchshil Hotels Pvt Ltd
ACE Villas
declared completion Dec 2026 · Jhamtani Realty Private Limited
Anandtara Iris Residences Phase I
declared completion Dec 2026 · Anandtara Infrastructure
Anandtara Iris Residences Phase II
declared completion Dec 2026 · Anandtara Infrastructure
Breeza
declared completion Dec 2026 · A AND A Developers
Emerald Bay Building 11
declared completion Dec 2026 · Pune Projects LLP
More builders in Mundhwa

Major developers building in Mundhwa

More projects in Pune

Other RERA-registered projects in Pune

Kool Homes Solitaire
declared completion Dec 2030 · Repton Properties Private Limited
Kool Homes Solitaire Phase II
declared completion Dec 2030 · Repton Properties Private Limited
Kool Homes Solitaire Phase III
declared completion Jun 2030 · Repton Properties Private Limited
Kosha
declared completion Aug 2029 · Hydepark Developers LLP
Kosmic Kourtyard Phase 1
declared completion Dec 2025 · Triaa Lifespaces LLP
Kosmic Kourtyard Phase 2
declared completion Dec 2028 · Triaa Lifespaces LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.