MahaRERA Property Intelligence · Pune

Tropica Phase II

P52100008711 · promoter Om Developers Project

The Drawings Report · ₹4,999

Which home should you ask for in Tropica Phase II?

We read all 16 approved drawings and 10 filed papers on this project’s RERA file — the sheets the builder filed to get it approved.

Completion date revised 5 times.

  • Which home to ask for — and which to say no to
  • What the drawings put around it
  • What to get in writing before you pay a booking amount

One real find, from a Gurugram colony’s approved papers: 392.997 sq m already used of the 396 allowed — the promised extra room can never be built.

Get it for this project →

Not useful to your decision? Full refund — no questions asked. Sent as a PDF in one working day.

Free before you decide: the 14 things to get in writing before you book

Every item comes from a real RERA filing. Send it to the family group before anyone pays a token.

Read it here →

Delivery and registration

When is the project declared for completion?

Tropica Phase II is registered with MahaRERA as P52100008711 and the promoter has declared completion for 30 Sep 2024.

30 Sep 2024

declared completion

24months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100008711
Registered on19 Aug 2017
Promoter-declared completion30 Sep 2024
Current statusCertificate Signed
Against todayabout 24 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Tropica Phase II record 29 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

Promoter record

What else is this promoter on record for?

Om Developers Project is the promoter of record on 29 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

29projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Tropica Phase II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
Building E1G+1331 Jan 2022
Building F1G+1331 Jan 2022
Building H1G+1330 Jul 2020

Legal and disputes

What disputes are disclosed?

17 complaints are on the MahaRERA record for Tropica Phase II, with orders passed in 17 of them.

17complaints

17with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000025895102/06/2023shirish govind sukhatme vs M/S Om Developerorder passed
CC00500000004363106/12/2019Barun Kumar Singh vs Atul Ratnakar Mahashabdeorder passed
CC00500000005390112/01/2020Shripad Vijay Katkamwar vs Mr. Atul Ratnakar Mahashabdeorder passed
CC00500000007512210/06/2021Ravi Pant vs Devendra Arvind Awatiorder passed
CC00500000008541301/04/2021Vinay Vasant Bhalerao vs Tropica Phase II ThroughMr. Devendra Awatiorder passed
CC00500000008542118/04/2021Girish Gautam Kate vs Devendra Arvind Awatiorder passed
CC00500000008568117/01/2022Manish Kumar vs Devendra Arvind Awatiorder passed
CC00500000008566711/06/2021Prasad Nandkumar Pagar vs Devendra Arvind Awatiorder passed
CC00500000010643526/01/2022Charudatta Jagannath Andhare vs Atul Ratnakar Mahashabde, Devendra Arvind Awati (M/S OM developers)order passed
CC00500000010644105/03/2022Suhas Deshmukh vs Ravishankar Shashikant Sahasrabuddheorder passed
CC00500000010650719/01/2022Himanshu Gambhire vs OM Developer Through Promoter Mr. Atul Mahashabdeorder passed
CC00500000010666508/03/2022Rupesh Dhule vs Devendra Awati, Atul Mahashabhdeorder passed
CC00500000010666708/03/2022Srikakolapu Venkata Mohana Krishna vs Devendra Awati, Atul Mahashabdeorder passed
CC00500000010685528/03/2022Lalit Rade vs Atul Ratnakar Mahashabdeorder passed
CC00500000027983910/12/2023Navnath Vitthal Bhise vs Mr. Devendra Arvind Awatiorder passed
CC00500000027994225/12/2023SUNIL SHANKARRAO BANDAL vs DEVENDRA ARVIND AWATIorder passed
CC00500000028997129/12/2023Nikhil Anil Golande vs Devendra Autiorder passed

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Karande Court13662015Pending For Evidence
Bhosale Court22462014Hearing Before Charge
Paldewar Court9942012Argument On Exhibit

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 5 times, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2021DUE TO PANDAMIC LABOUR SHORTAGE WE COULD NOT ACHIEVE COMPLETION STAGE. OUT OF 3 BUILDINGS WE HAVE COMPLETED ONE BUILDING i.e.H Building.Applying for completion. We have completed r
31 Jul 202130 Apr 2022DUE TO PANDAMIC LABOUR SHORTAGE WE COULD NOT ACHIEVE COMPLETION STAGE. OUT OF 3 BUILDINGS WE HAVE COMPLETED ONE BUILDING i.e.H Building.Applying for completion. We have completed r
30 Apr 202230 Jul 2022DUE TO COVID SUFFER FINACIAL CRUNCH AND NO NEW BOOKING .
30 Jul 202231 Jul 2023WE ARE UNABLE TO COMPLETE WHITEN SAID TIME PERIOD ,BECAUSE COVID EFFECT ON OUR PROJECT & TODAYS LABOUR COST ,MATERIEL COST RISE .SO PLEASE EXTENSION OUR RERA COMPLETION DATE.
31 Jul 202330 Sep 2024SOME OUR FINANCIAL ISSUE BECAUSE WE ARE CLOSED IIFL CONSTRUCTION LOAN & CUSTOMER BOOKING ARE VERY DOWN THERE IS WE ARE UNABLE COMPLETE OUR PROJECT.

Location, Land & Connectivity

Located at Haveli, Pune, 412101. Per the filed land record, the plot is bounded to the north by 18 DP road and S No 58-2, to the south by 18 DP Road and S No 56-2 and 54, to the east by S No 59 and 53 and 56-2 and to the west by 58-1 part and 57-1B part and 56-1A part. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park7 km
Baner–Balewadi belt11 km
Pune Junction / city centre20 km
Pune Int'l Airport (Lohegaon)21 km
Kharadi / EON IT Park25 km
Magarpatta / Hadapsar IT25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 What I’d do as a buyer here · Drawings Report

The report opens with what this project really is — read from its approved drawings — then the specific calls: the cheapest good way to buy here, the home to say no to, what you can stop worrying about, and what to get in writing before you sign anything.

Unlock in the ₹4,999 report →

Site & infrastructure

What this project's sanctioned plan shows — read for you
Where the plan is legible, the full report reads this project's layout plan filed with MahaRERA and lays out what's on it: where the utilities and open space sit, how the site is laid out around them, and which way it faces. When a plan can't be read clearly, we tell you plainly rather than guess.
In the full report:Open space · Utilities · Orientation · Layout
See what the full read covers ↓or read a sample report first →

🔒 Which home to ask for · Drawings Report

The home-level read: which ones to prefer and which to avoid, what the drawings put around each, and the things on this site nobody at the sales desk will tell you about.

Unlock in the ₹4,999 report →

The approved drawings

16approved drawings on file
10other papers filed

Everything above is on this page already, free, from the government record. The drawings are different: the 16 approved sheets are the same drawings the builder filed to get Tropica Phase II approved — what sits under each tower, which floor holds machines, what the sales sheet leaves out. Nobody reads them for you. We do.

What that turns up — from other projects’ filings:

ATS Knightsbridge · Sector 124, Noida

You pay for 10,000 sq ft. The floor inside your home is 6,982 sq ft. The rest is walls, shared circulation and services. Get both numbers written into your agreement before you pay any booking amount.

Oberoi Elysian · Goregaon East, Mumbai

“The building is complete.” The tower has reached full height — true. The same filed certificate, same page: sanitary fittings 6% done. Ask for a possession date in writing.

Godrej Aristocrat · Sector 49, Gurugram

Paying extra for the top floor? The terrace drawing shows what sits on the slab above those flats: the overhead water tanks, the lift machine rooms and the roof machinery. Ask which flat sits under which.

Prestige Camden Gardens · Thanisandra, Bengaluru

The approved parking table asks for 12 visitor spaces. It shows 0. Two-wheeler spaces: also 0. Ask in writing where visitors will park.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Om Developers Project Ravet is the promoter on 3 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Om Developers Project Ravet

Om Developers Project Ravet
Past its declared completion datePune

Other RERA-registered projects in Ravet

City ONE Skyve
possession by Sep 2026 · Shree SAI Capital
Godrej Carnival
possession by Sep 2026 · Godrej Skyline Developers Limited
Godrej Nurture
possession by Sep 2026 · Godrej Skyline Developers Limited
Madhuban
possession by Sep 2026 · Godrej Skyline Developers Limited
OM Mangalam Chaitanya
possession by Sep 2026 · Shri Associates
OM Mangalam Disha
possession by Sep 2026 · Shri Associates

Major developers building in Ravet

Other RERA-registered projects in Pune

Tropica Phase III
declared completion Jul 2022 · Om Developers Project Ravet
Trove
declared completion Sep 2024 · Kalash Properties
TRU Meadows D
possession by Mar 2028 · FAB Five Realty LLP
Trump World Center Pune
possession by Dec 2031 · Enbrick Properties LLP
Truspace Platina
declared completion Aug 2026 · Atharva Developments
Truspace Premiera
declared completion Sep 2025 · Atharva Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 10 Sep 2026