Pune/Project record

MahaRERA · the public record

UNNATI VATIKA

KOREGAON MUL · M/S UNNATI LIFESPACE

Is this the right project?
Which plot should you choose?

Read the free RERA facts below. For help choosing a plot or comparing a price, select a report.

See the report before you buy

Avoid bad decisions, only go for the best plots.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
23units filed as unsoldInventory · 17 October 2026
30 Apr 2027declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for UNNATI VATIKA

MahaRERA · PP1260002500646

Delivery and registration

When is the project declared for completion?

UNNATI VATIKA is registered with MahaRERA as PP1260002500646 and the promoter has declared completion for 30 Apr 2027.

30 Apr 2027

declared completion

6months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationPP1260002500646
Registered on25 Aug 2025
Promoter-declared completion30 Apr 2027
Current statusCertificate Signed
Against today6 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for UNNATI VATIKA record 3 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 19 Jul 2026

  • Filing progress reports — 3 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In UNNATI VATIKA, ₹3.68 Cr of a declared ₹4.75 Cr estimated project cost is reported as incurred, about 77.5%, as at the last certified filing with MahaRERA.

77.5%

₹3.68 Cr

of ₹4.75 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 19 Jul 2026

Sales

How many are filed as sold or booked?

In UNNATI VATIKA, 0 of 34 plots filed with MahaRERA are recorded as sold or booked, about 0%, and 34 are filed as unsold.

0%sold or booked

0 of 34 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 19 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for UNNATI VATIKA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 17 October 2026

What the filings record, plot by plot

Read from MahaRERA on 17 October 2026

No plot in UNNATI VATIKA carries a filed agreement value in this unit list. What the promoter has filed is the government ready reckoner value for 34 plots — the Annual Statement of Rates valuation, with each plot’s filed area already applied. Across them that is Rs 511 a sq ft typical, over Rs 511 to Rs 511.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the plot to you.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2027At present, construction work on the said project is on hold due to delays caused by material shortages, labour shortages, and legal and technical issues. The project has therefore

Location, Land & Connectivity

Located at KOREGAON MUL, KOREGAON MUL, Pune City, Pune, 412110. Per the filed land record, the plot is bounded to the north by GAT NO 102 PART, to the south by GAT NO 174, to the east by 105 M ROAD and to the west by GAT NO 163 PART. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 2 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Magarpatta / Hadapsar IT2 km
Kharadi / EON IT Park3 km
Pune Junction / city centre4 km
Pune Int'l Airport (Lohegaon)6 km
Baner–Balewadi belt15 km
Hinjewadi Rajiv Gandhi IT Park20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Theur

Vintage City Ph 2
declared completion Dec 2026 · Eiffel Landmarks Private Limited
MK Estrella
declared completion Feb 2027 · Mayra Properties
Nivaan Sparsh Phase-1
declared completion Jun 2027 · Not Available
Nivaan Sparsh II
declared completion Dec 2027 · Shahaji Sakharam Sawant
Goodland Phase-III
declared completion Jan 2028 · Goodland Realty Private Limited
Dream City
declared completion Jul 2028 · Not Available
More projects in Pune

Other RERA-registered projects in Pune

UP-Life-Phase-1-Veronica
declared completion Jun 2025 · Avior Shelters LLP
UP-Life-Phase-2-Emerald
declared completion Dec 2029 · Avior Shelters LLP
UP-Life-Phase-3-Sapphire
declared completion Dec 2025 · Avior Shelters LLP
UP-Life-Phase-4-Lavender
declared completion Dec 2025 · Avior Shelters LLP
UP-Life-Phase-5-Ivory
declared completion Dec 2029 · Avior Shelters LLP
UP-Life - Phase - 6 - F - Magenta
declared completion Dec 2029 · Avior Shelters LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.