Vishal Heights

Pune · Balaji Builders

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Vishal Heights

MahaRERA · P52100013728

Delivery and registration

When is the project declared for completion?

Vishal Heights is registered with MahaRERA as P52100013728 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100013728
Registered on25 Oct 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Vishal Heights record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

Balaji Builders is the promoter of record on 7 projects registered with MahaRERA.

7projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Vishal Heights in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
Existing Structure1G+0-
Vishal Heighs A-wing1G+3-
Vishal Heights B-wing1G+2-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2022Due to Economical slow down in market flat and shops shall not booked by customer so the work has been stopped due to financial problem.

Location, Land & Connectivity

Located at Haveli, Pune, 411021. Per the filed land record, the plot is bounded to the north by Ramnagar Colony, to the south by Tapowan Society, to the east by NDA Road and to the west by Ramnagar Colony. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 4 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Baner–Balewadi belt4 km
Hinjewadi Rajiv Gandhi IT Park9 km
Pune Junction / city centre10 km
Magarpatta / Hadapsar IT16 km
Pune Int'l Airport (Lohegaon)16 km
Kharadi / EON IT Park17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Balaji Builders project & its RERA track record →

Other RERA-registered projects in Pashan

Marvel Selva Ridge Villa 6, 9, 11, 12
Developer in insolvency (NCLT) · declared completion Dec 2026 · Marvel Omega Builders PVT LTD
Reelicon Fairy Bell
declared completion Dec 2026 · Reelicon Red Homes Private Limited
Green Mint
declared completion Dec 2026 · Sunil Vishwanath Salunke
Neelanchal Phase I
Not filing quarterly progress reports · declared completion Dec 2026 · Pinnacle Vastunirman Pvt. Ltd
Neelanchal Phase II
declared completion Dec 2026 · Pinnacle Vastunirman Pvt. Ltd
27th Avenue NXT
declared completion Dec 2026 · Blue Construction Company
More builders in Pashan

Major developers building in Pashan

More projects in Pune

Other RERA-registered projects in Pune

Vishal Leela Residency
declared completion Dec 2025 · Sopan Gahinaji Lanke
Vishal Residency B Wing
declared completion Mar 2022 · Vision Builders AND Developers
Vishalata Nisarg
declared completion Feb 2025 · V. S. Bondre Developers (promoters &
Vishalleela Residency
declared completion Mar 2027 · S.g.lanke Construction CO
Vishnu
declared completion Feb 2025 · VG Realtors LLP
Vishnu
declared completion Dec 2028 · Varada Dream Homes

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.