Pune/Project record

MahaRERA · the public record

YASHOBHOOMI

WADMUKHWADI · RADHESHYAM RAMESHWARDAS AGARWAL

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Sep 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for YASHOBHOOMI

MahaRERA · P52100022916

Delivery and registration

When is the project declared for completion?

YASHOBHOOMI is registered with MahaRERA as P52100022916 and the promoter has declared completion for 30 Sep 2023.

30 Sep 2023

declared completion

37months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100022916
Registered on01 Nov 2019
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 37 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for YASHOBHOOMI record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

RADHESHYAM RAMESHWARDAS AGARWAL is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for YASHOBHOOMI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
BUILDING A1G+1230 Mar 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Filed descriptions (status fields empty): 1 “PENDING”. These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Cjsd District Court Pune18/20182018Status not supplied
Filed description: PENDING

Location, Land & Connectivity

Located at WADMUKHWADI, EXIST ROAD, Haveli, Pune, 412105. Per the filed land record, the plot is bounded to the north by SAVITA SANJAY AGARWAL, to the south by EXISTING ROAD, to the east by 180 P and to the west by 180 1 2. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 159 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)158 km
Kharadi / EON IT Park159 km
Magarpatta / Hadapsar IT162 km
Pune Junction / city centre166 km
Baner–Balewadi belt172 km
Hinjewadi Rajiv Gandhi IT Park174 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Moshi

Anantam Skyone
declared completion Oct 2026 · Rajshree Landmark LLP
Excel Celestia Residency E AND F AND Mhada
declared completion Oct 2026 · Excel Housing
Skyline Pride
declared completion Oct 2026 · Ajit Dnyaneshwar Pawar
THE Business Gate
declared completion Oct 2026 · Kesar Vasudev Properties
Stella B1
declared completion Nov 2026 · DMK Infrastructure PVT LTD
Clone Tiara
declared completion Nov 2026 · Clone Properties LLP
More builders in Moshi

Major developers building in Moshi

More projects in Pune

Other RERA-registered projects in Pune

Yashobhoomi B
declared completion Jun 2024 · Radheshyam Rameshwardas Agarwal
Yashobhoomi Phase II
declared completion Dec 2026 · Rameshwar Constructions
Yashoda
declared completion Jan 2029 · Mrunal Promoters & Developers LLP
Yashoda Aangan
declared completion Jun 2023 · Konark Associates
Yashoda Complex
declared completion Dec 2024 · Chaitanya Mahadev Ghule
Yashoda Heights
declared completion Nov 2026 · Paras Shivajirao Dhore

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.