Bangalore/Project record

K-RERA · the public record

MARIGOLD

· SHIRGURKAR REAALTYY

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
37%construction reportedQ3 2025 filing
22units not bookedof 23 · Q3 2025 filing
23registered unitsK-RERA registration · read 16 Jul 2026

Free project details

Registration read 16 Jul 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q3 2025

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 16 Jul 2026

Registered units and project size

PH-04
1
2BHK
1
1BHK
4
2BHK
1
PH-03
1
2BHK
4
3BHK
1
3BHK
4
1RK
1
PH-02
1
2BHK
4

Filed categories, unchanged · K-RERA registration · read 16 Jul 2026

The whole registration

0.1registered acres

187.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for MARIGOLD

K-RERA · PRM/KA/RERA/1249/447/PR/050525/007711

Project facts and comparisons

On the register

Land area496 sq m (0.1 acres)
Homes registered23
Tower/wing entries1
Unit mix1 × PH-04, 10 × 2BHK, 4 × 1BHK, 1 × PH-03, 5 × 3BHK, 1 × 1RK, 1 × PH-02

In context

Density187.7 homes per acre
Density in context96th percentile of 4913 projects in this register (median 82)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units23Total inventory registered with K-RERA.
Official carpet area1,561 sqmTotal carpet area reported for the project.
Official built-up area1,972 sqmUseful scale context when comparing density and project cost.
Registered land area496 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.35Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)10Separate filed counts; these categories may overlap and are not added together.
Covered-parking field10Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBGM-LBPAS-2137/23-24/BPUse this to match the sanctioned drawing set shown by the builder.
Plan approval date31-07-2023
Project start date15-08-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
PH-0414%20 sqm
2BHK14%67 sqm
1BHK417%33 sqm
2BHK14%55 sqm
PH-0314%52 sqm
2BHK417%64 sqm
3BHK14%78 sqm
3BHK417%83 sqm
1RK14%25 sqm
PH-0214%26 sqm
2BHK417%57 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
MARIGOLD5231014.94 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 23 official flat/unit rows, matching the 23 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK1055.0-66.7 sqm19.0-24.2 sqm0 (10 with 0)
3 BHK578.0-83.0 sqm27.1-33.6 sqm0 (5 with 0)
1 BHK432.9 sqm12.3 sqm0 (4 with 0)
PENT HOUSE320.7-52.5 sqm8.4-18.7 sqm0 (3 with 0)
NA125.6 sqm8.9 sqm0 (1 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
MARIGOLD2320.7-83.0 sqm8.4-33.6 sqm0 (23 with 0)
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
G-1MARIGOLD02 BHK55.0 sqm19.0 sqm0
G-2MARIGOLD02 BHK66.7 sqm22.9 sqm0
G-3MARIGOLD0NA25.6 sqm8.9 sqm0
G-4MARIGOLD03 BHK78.0 sqm27.1 sqm0
F-101MARIGOLD12 BHK65.7 sqm23.9 sqm0
F-102MARIGOLD12 BHK64.5 sqm24.2 sqm0

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

9 of 31 compliance document slots are filed as Not Applicable; the remaining 22 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

See the filed approval statuses and linked documents →

Statutory approval status

RERA filing

2 of 2 applicable approvals are marked Approved in the filing. Check the linked documents for their scope and validity.

8 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved09-01-2025Marigold Water NOC 09012025.pdf
KPTCL- BESCOMApproved30-03-2022HESCOM- NOC 30032022.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantRAJENDRA MUNDADA0280051994Belagavi, Karnataka - 590011
EngineerVINAY BEHEREKBPAS-REG-7374/18-191997Belagavi, Karnataka - 590006
ArchitectNITIN SHIRGURKARBGM/BL/338/2019-202019Belagavi, Karnataka - 590006
ContractorSHIRGURKAR REALTYY PVT LTD-2017Belagavi, Karnataka - 590006

Builder track record

RERA filing

Shirgurkar Reaaltyy has 2 other K-RERA-registered projects in our records. 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q3): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress37% → 37% (+0 pts)
Units sold/booked as registered1/23 (4%)
Buyer collections in available QPRs₹0.00 Cr
  • The builder has drawn 0.00x of buyer collections from escrow (about 0% of the ₹0 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹10.9 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: Industrial Development Bank of India. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 457 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Kempegowda Int'l Airport452 km
Outer Ring Road / Manyata457 km
MG Road / city centre461 km
Bellandur–Marathahalli belt471 km
Whitefield IT hub473 km
Electronic City475 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Shirgurkar Reaaltyy.
Shirgurkar Reaaltyy has 3 projects registered in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Byatarayanapura

Sobha Dream Gardens Phase 3 - Wing 3 And 4
Olivia AT Raintree Boulevard - Cluster 6

Major developers building in Byatarayanapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 16 Jul 2026. Document and inventory dates are shown in their sections.