Purva Westend 2 (Block F)

Bengaluru South · Purva Star Properties

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
31 Mar 2022declared completionK-RERA registration · read 25 Oct 2026
55registered unitsK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Registered units and project size

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

0.3registered acres

160.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for Purva Westend 2 (Block F)

K-RERA · PRM/KA/RERA/1251/310/PR/190129/002310

Project facts and comparisons

On the register

Declared completion31 March 2022
Land area1,383 sq m (0.3 acres)
Homes registered55
Tower/wing entries1

In context

Density160.9 homes per acre
Density in context97th percentile of 791 Bengaluru South projects (median 77.3)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units55Total inventory registered with K-RERA.
Registered land area1,383 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)55Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date31-03-2019

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Block F65555-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 55 official flat/unit rows, matching the 55 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK3072.0-100.0 sqm0.0 sqm30
3BHK25115.0-121.0 sqm0.0 sqm25

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Block F5572.0-121.0 sqm0.0 sqm55
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
001Block F02BHK82.0 sqm0.0 sqm1
002Block F03BHK115.0 sqm0.0 sqm1
003Block F03BHK121.0 sqm0.0 sqm1
005Block F02BHK72.0 sqm0.0 sqm1
006Block F03BHK115.0 sqm0.0 sqm1
007Block F03BHK115.0 sqm0.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

All 20 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Mar 2022, extended (Covid Extension) to 31 Dec 2022 — both dates have passed with no OC on file. An extension application filed on 22 Dec 2022 is pending with K-RERA — until it is approved, the registration stands lapsed.

Approval documents

Electricity (BESCOM/ESCOM)Not identified in the document list
Water & sewage (BWSSB/KWSSB)Document listed: BWSSB
Fire NOCDocument listed: Fire Force Department
Pollution control (KSPCB)Not identified in the document list
Environmental clearanceDocument listed: SEIAA
Airport Authority height clearanceDocument listed: Airport Authority of India

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (7 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
BHARATH C vs M/S PURVA STAR PROPERTIES PRIVATE LIMITEDRequesting for full refund of the advance amount and compensation for delaying the advance for more than 6 months.AUTHORITY20/09/2023
VEER SHUBHRANSHU SHRIVASTAVA & ANOTHER vs PURVA STAR PROPERTIES PRIVATE LIMITED, H. P. RAMA REDDYDirection to register the Sale Deed and delay period interest and as prayed in the detailed ComplaintAUTHORITY08/01/2024
RAJAT AGARWAL & ANOTHER vs PURVA STAR PROPERTIES PRIVATE LIMITED & ANOTHERHandover physical possession of apartment bearing No. F-002 by duly executing and registering the Sale Deed + delay period interest to the Complainants calculated on a sum Rs.1,01,11,150/-AUTHORITY06/09/2024
Sujit Kumar Piri vs Purva Star Properties Private Limited & anotherHandover physical possession of apartment by duly executing and registering the Sale Deed + pay delay period interest to the Complainants calculated on a sum Rs.1,11,48,516/-AUTHORITY06/09/2024
MOULEESWARAN RAJARAM & ANOTHER vs PURVA STAR PROPERITIES PRIVATE LIMITED & ANOTHERHandover physical possession of apartment bearing No. F-403 by duly executing and registering the Sale Deed + Pay delay period interest to the Complainants calculated on a sum Rs.1,18,50,000/-AUTHORITY06/09/2024
SRIKANTH KURRA vs PURVA STAR PROPERTIES PRIVATE LIMITED & ANOTHERHandover physical possession of apartment bearing No. F-305 by registering the Sale Deed + Pay delay period interest to the Complainants calculated on a sum Rs.59,61,061.41 /-AUTHORITY06/09/2024
SANTHOSH ARJUN NUTHANAGANTI & ANOTHER vs PURVA STAR PROPERTIES PRIVATE LIMITED & ANOTHERDirection to register the Sale Deed and pay delay period interest and as prayed in the detailed complaintAUTHORITY06/09/2024

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (47 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190209/0002082
09-02-2019
Delay in delivery of the apartmentPurva Westend (another project by this promoter)DISPOSED AO
CMP/190307/0002386
07-03-2019
Delay in delivery of the apartmentPurva Westend (another project by this promoter)DISPOSED AO
CMP/190309/0002399
09-03-2019
Non Adherence to Handover timeline as per AgreementPurva Westend (another project by this promoter)DISPOSED AO
CMP/190309/0002402
09-03-2019
Non Adherence to Handover timeline as per AgreementPurva Westend (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/190311/0002401
11-03-2019
Non adherence to handover and not agreeing to pay the RERA penalty.Purva Westend (another project by this promoter)DISPOSED AO
CMP/190312/0002377
12-03-2019
Delay in project delivery and not agreeing to pay RERA penalityPurva Westend (another project by this promoter)DISPOSED AO
CMP/190407/0002575
07-04-2019
Delay for delivery of the project and compensation to be paid as per RERA GuidelinesPurva Westend (another project by this promoter)DISPOSED AO
CMP/190411/0002614
11-04-2019
Delay in handover and compensation issuesPurva Westend (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹72.3 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: HDFC Richmond Road Branch (IFSC HDFC0000523, a/c …9527). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 5 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Electronic City5 km
Bellandur–Marathahalli belt7 km
MG Road / city centre10 km
Whitefield IT hub15 km
Outer Ring Road / Manyata17 km
Kempegowda Int'l Airport35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Purva Star.
Purva Star has 2 projects registered in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Singasandra

Major developers building in Singasandra

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.