RERA Property Intelligence Report · Preview

RAJA RITZ AVENUE - PHASE 1

RAJA HOUSING · Bengaluru East · K-RERA PRM/KA/RERA/1251/446/PR/171028/001242

The Drawings Report · ₹4,999

Which flat should you ask for in RAJA RITZ AVENUE - PHASE 1?

We read all 5 approved drawings and 36 filed papers on this project’s RERA file — the sheets the builder filed to get it approved.

  • Which flat to ask for — and which to say no to
  • What the drawings put above, below and beside it
  • What to get in writing before you pay a booking amount

One real find, from a Noida project’s approved drawings: the buyer pays for 10,000 sq ft — the floor inside the flat is 6,982 sq ft.

Get it for this project →

Not useful to your decision? Full refund — no questions asked. Sent as a PDF in one working day.

Not yet
Completion certificate
None declared
Legal status
7
Other RERA projects by builder

Free before you decide: the 14 things to get in writing before you book

Every item comes from a real RERA filing. Send it to the family group before anyone pays a token.

Read it here →

This project, on the record

RAJA RITZ AVENUE - PHASE 1 covers 3.5 acres with 5 towers and 220 registered homes, featuring 10 one-bedroom units. At 62.9 homes per acre it sits at the 32nd percentile of 1118 Bengaluru East projects on this register (median 75.7). Its declared completion date of 31 January 2021 has passed; no occupancy certificate is on record.

Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 January 2021
Land area14,144 sq m (3.5 acres)
Homes registered220
Towers5
Unit mix10 × 1 BHK

In context

Density62.9 homes per acre
Density in context32nd percentile of 1118 Bengaluru East projects (median 75.7)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

What you can verify free on this page

The official K-RERA filing record, in plain English

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Legal status, approvals & the project team
  • Financials & construction progress from the quarterly filings
  • Location & connectivity

Registration and delivery

What does the register record for this project?

Raja Ritz Avenue - Phase 1 is registered with K-RERA as PRM/KA/RERA/1251/446/PR/171028/001242, and the promoter has declared completion for 31 Jan 2021.

31 Jan 2021

declared completion

Figures are the promoter's own filings as they stood when Quietlist last read the register. A declared completion date is a filing, not a handover commitment.

Source · K-RERA project register · read 10 Sep 2026

Project scale

How big is the project, and what is it declared to cost?

Raja Ritz Avenue - Phase 1 spans 14,144 sq m (3.50 acres), comprises 5 towers, registers 220 units, and is declared to cost ₹72.02 cr.

₹72.02 cr

declared project cost

3.50acres

14,144 sq m

220units

on the registration

2.0FAR

sanctioned

Scale and cost as the promoter registered them. The declared cost is the promoter's own estimate on the filing, not a valuation and not a price to a buyer.

Source · K-RERA project registration · read 10 Sep 2026

Promoter record

What else is this promoter on record for?

Raja Housing is the promoter of record on 7 projects registered with K-RERA, 4 of which are past their declared completion dates on the register.

7projects

registered with K-RERA

4past declared date

on the register

52%

average construction reported

Counted across Quietlist's full K-RERA register store, matched on the promoter name as it appears on each filing.

Source · K-RERA register, all projects · read 10 Sep 2026

🔒 What I’d do as a buyer here · Drawings Report

The report opens with what this project really is — read from its approved drawings — then the specific calls: the cheapest good way to buy here, the flat to say no to, what you can stop worrying about, and what to get in writing before you sign anything.

Unlock in the ₹4,999 report →

220
Registered units
₹72.0 Cr
Est. construction cost
Units profiled
41
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units220Total inventory registered with K-RERA.
Official carpet area510 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area14,144 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings5Official tower/wing count in the K-RERA detail page.
Parking disclosed1,400 total (0 open) — 6.36 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date01-08-2017

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
1 BHK10100%510 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Block 5450280-
block 6450280-
block 7440280-
block 8440280-
block 9440280-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 220 official flat/unit rows, matching the 220 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK114745.4-999.2 sqft290,850.0 sqft114
3BHK95875.3-1,139.6 sqft290,850.0 sqft95
1BHK10476.2-594.9 sqft290,850.0 sqft10
2.5BHK1875.3 sqft290,850.0 sqft1

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Block 550477.7-1,004.2 sqft290,850.0 sqft50
block 650476.2-1,005.2 sqft290,850.0 sqft50
block 740593.2-1,139.6 sqft290,850.0 sqft40
block 840593.2-1,139.6 sqft290,850.0 sqft40
block 940593.2-1,139.6 sqft290,850.0 sqft40
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1Block 503BHK1,000.0 sqft290,850.0 sqft1
2Block 503BHK1,003.6 sqft290,850.0 sqft1
3Block 501BHK477.7 sqft290,850.0 sqft1
4Block 502BHK788.1 sqft290,850.0 sqft1
5Block 502BHK745.8 sqft290,850.0 sqft1
6Block 502BHK745.8 sqft290,850.0 sqft1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~926 sqft — mid-format homes (2–3BHK territory), not compact stock. This is a large, multi-tower township — 220 homes across 5 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 1,400 parking spaces for 220 homes (~6.4 per home) — comfortable headroom over the 1-per-home many projects offer.
Your land share (UDS)Undivided land share averages ~290850 sqft per home; across all 220 homes that is ~42029% of the plot — the undivided shares sum to more than the plot area, which can indicate an extraction error in our reading rather than a filed figure.

Site & infrastructure

What this project's sanctioned plan shows — read for you
Where the plan is legible, the full report reads this project's layout plan filed with K-RERA and lays out what's on it: where the utilities and open space sit, how the site is laid out around them, and which way it faces. When a plan can't be read clearly, we tell you plainly rather than guess.
In the full report:Open space · Utilities · Orientation · Layout
See what the full read covers ↓or read a sample report first →

🔒 Which flat to ask for · Drawings Report

The flat-level read: which towers and floors to prefer and which to avoid, what the drawings put above, below and beside each flat, and the things on this site nobody at the sales desk will tell you about.

Unlock in the ₹4,999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 36 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Jan 2021, extended (Section 6 Extension) to 31 Oct 2022 — both dates have passed with no OC on file. The extension on file was granted on 27 Dec 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/446/PR/221227/001242) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (29 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
RATHIN PAUL vs RAJA HOUSING LIMITED1. Raja housing Ltd should start paying me compensation starting from 1Nov2021 till the project completion date. 2. Requesting RERA to not provide further extension of completion date to this project.AUTHORITY28/11/2022
JYOTI RANJAN MOHANTY & PRIYA SHARMA vs RAJA HOUSING LIMITED1. Please ensure that the project completes on time and we get compensation for each delayed period. Please do not provide any extension to the project as the delay seems very much intentional.AUTHORITY27/09/2022
ARIJIT DEY vs RAJA HOUSING LIMITED1. Raja Housing Limited should start paying me delayed compensation as per sales agreement from 1st November 2021till project completion date. 2. Requesting RERA to not provide any further extensionAUTHORITY27/09/2022
KARTHI J & MRS. GOWRI SANKARI vs RAJA HOUSING LIMITEDSettlement of Delay Compensation till the date of receiving OC / Registration and proper full Handover.AUTHORITY21/12/2022
SantoshKumar N V vs Raja Housing LimitedNeed Compensation amount from Sept 2020 till dateAUTHORITY21/03/2023
Vikash Gupta vs RAJA HOUSING LIMITEDRaja Housing Ltd should pay compensation as per agreement from November 2021 till the possession date.AUTHORITY19/12/2022
Suresh Turkani vs RAJA HOUSING LIMITEDNo extension should be provided to builder and intervention needed to ensure builder adhere to RERA and deliver flat ASAP with compensation.AUTHORITY19/12/2022
Tanaya Jana vs RAJA HOUSING LIMITEDeither builder should pay the due compensation or they must adjust it with next disbursement.AUTHORITY19/12/2022
Sapna Ks vs RAJA HOUSING LIMITEDRequesting nowAUTHORITY19/12/2022
Nithya Priya K R vs RAJA HOUSING LIMITED1. Compensation(SBI MCLR 2%/month) to be paid from Aug 2021 before reg. 2. Builder should be prohibited from collecting maintenance before completing amenities 3. No further project extension by RERAAUTHORITY19/12/2022
Raja Ravi Kiran Yeluri vs RAJA HOUSING LIMITED1) Deny phase 1 extension approvals sought by RHL. 2) Compensation for the delay as per the agreement 3) Instruct RHL to update correct status in RERA website and to customersAUTHORITY16/11/2022
NITIN BANSAL vs RAJA HOUSING LIMITEDRaja Housing Ltd should start paying me the compenstation starting from 1 Nov 2021 till the project completion date. Requesting RERA to not provide further extension to this project.AUTHORITY15/09/2022
Priyanshu Shrivastava vs RAJA HOUSING LIMITED1. Final Possession date 2. correct compensation as per agreement i.e monthly basis starting Nov 21 3. No further extension provided to the builder. 4. RERA website to be updated as per actualsAUTHORITY14/12/2022
SHURYA KUMAR vs M/S RAJA HOUSING LIMITEDThe builder has to pay the delay compensation from January 2021 till OC is received.AUTHORITY14/12/2022
MANOJ KUMAR YADAV & TANNU SHREE vs RAJA HOUSING LIMITEDCompensation for almost 1 Year delay from Builder and compel builder to follow Agreement and RERA guidelines before possession. Not give extension to RAJA RITZ Avenue phase 1.AUTHORITY13/10/2022
DEBASISH DWIBEDY & MRS. SASWATI DAS vs RAJA HOUSING LIMITED1. Raja housing Ltd should start paying me compensation starting from 1Nov2021 till the project completion date. 2. Requesting RERA to not provide further extension of completion date to this projectAUTHORITY11/10/2022
ROHIT BADE vs RAJA RITZ AVENUE - PHASE 11. Request RERA to not provide further extension to builder. 2. Request RERA to force the builder to provide a clear project completion date and start providing compensation delay to customers.AUTHORITY10/10/2022
Akshaya Jeevan Panigrahi vs RAJA HOUSING LIMITEDTo order the Builder rectify the defect at its own cost as agreed on the Signed Sales Agreement/Sale deed or compensate the cost of Rs Two LakhAUTHORITY09/07/2025
RAVI RANJAN KUMAR vs M/S. RAJA HOUSING LIMITEDplease do not allow anymore extension and order them to pay monthly compensation for delaysAUTHORITY07/10/2022
SHANKAR RAMAN IYER vs RAJA HOUSING LIMITEDFirm Date on Handover in livable condition and compensation for delayAUTHORITY07/02/2023
KUMAR SAURABH & SANGEETA KUMAR SAURABH vs RAJA HOUSING LIMITEDExpedition of possession and payment from builder for the entitled compensation.AUTHORITY07/02/2023
KISHOR KUMAR vs RAJA HOUSING LIMITED1. Raja Housing ltd should pay me the compensation for delay starting from 1 Nov 2021 till project completion. 2. Request to RERA : Donot provide further extension of completion date to this project.AUTHORITY06/01/2023
ARJUN RAMAKRISHNAN, DIVYA K, B RAMAKRISHNAN vs M/S. RAJA HOUSING LIMITED1. Timely payment of monthly compensation till the date of registration. 2. Handing over of apartment as per date promised. 3. Please do not approve further extension for this project/builder.AUTHORITY05/12/2022
Xavier Mascarenhas vs RAJA HOUSING LIMITEDReturn all the money paid along with applicable interest rate based interest payments and penalties back to meAUTHORITY05/04/2023
KUSHI DHANANJAYA vs RAJA HOUSING LIMITEDPlease do not provide any further extension to the builder under force majure as the builder has been constantly give false promises and unrealistic delivery datesAUTHORITY04/08/2022
MR NAGA SURYA NARAYANA MAROJU & ANOTHER vs M/S.RAJA HOUSING LIMITED AND ANOTHERWe request RERA to help and get the compensation paid on a monthly basis and a concrete date for possession with the Occupancy Certificate and with all the promised amenities .AUTHORITY03/11/2023
MAHESH HEBBALLI & RASHMI ANGADI vs RAJA HOUSING LIMITEDProviding compensation from Raja Housing, for delayed Construction and handover of flatAUTHORITY02/11/2022
SOUMYA SINGARI & SAMBHU PRASAD BEJ vs RAJA HOUSING LIMITEDMonthly Compensation from the RERA expiry date as per the agreementAUTHORITY02/08/2022
PRADEEP KUMAR YADAV vs RAJA HOUSING LIMITEDBuilder should start paying me compensation from 1st Nov 2021 after RERA expiry date and no further extension should be provided to BuilderAUTHORITY01/08/2022

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (34 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/211111/0008542
11-11-2021
Project delayed and interest not paid by builderRAJA RITZ AVENUE - PHASE 1DISPOSED AUTHORITY BENCH4
CMP/211210/0008709
10-12-2021
Possession delayed and not paying compensationRAJA RITZ AVENUE - PHASE 1DISPOSED AUTHORITY BENCH6
CMP/220207/0008977
07-02-2022
Project delayed, builder is not responding and not paying compensation for the delay posessionRAJA RITZ AVENUE - PHASE 1DISPOSED AUTHORITY BENCH6
CMP/220209/0008994
09-02-2022
Delay in Delivery of Flat and deliberate delay in completion of projectRAJA RITZ AVENUE - PHASE 1DISPOSED AUTHORITY BENCH6
CMP/220215/0009005
15-02-2022
Possession delayed, not paying compensation and no proper communication from builderRAJA RITZ AVENUE - PHASE 1DISPOSED AUTHORITY BENCH6
CMP/220215/0009006
15-02-2022
My property is not handed over by RERA pocession dateRAJA RITZ AVENUE - PHASE 1DISPOSED AUTHORITY BENCH6
CMP/220215/0009014
15-02-2022
Possession delayed and not paying compensationRAJA RITZ AVENUE - PHASE 1DISPOSED AUTHORITY BENCH6
CMP/220218/0009024
18-02-2022
Rera date expired, possession delayed and compensation not paidRAJA RITZ AVENUE - PHASE 1DISPOSED AUTHORITY BENCH6

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectMr. JAGALUR.F.F - SPACEMAST-1997Vyalikaval, GD Park Extention
ContractorM/s UMIYA CONSTRUCTIONS-2009Nobel Residency, Yelanahalli
Structural engineerMr. M THARANATH - RACHANA CONSULTANTS---

Builder track record

RERA filing

Raja Housing has 7 other K-RERA-registered projects in our records (average reported construction progress 52%). 4 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹32.7 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC RICHMOND ROAD, BANGALORE – 560025 (IFSC HDFC0000523, a/c …2031). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub4 km
Bellandur–Marathahalli belt7 km
MG Road / city centre12 km
Outer Ring Road / Manyata12 km
Electronic City17 km
Kempegowda Int'l Airport24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

The approved drawings

5approved drawings on file
36other papers filed

Everything above is on this page already, free, from the government record. The drawings are different: the 5 approved sheets are the same drawings the builder filed to get RAJA RITZ AVENUE - PHASE 1 approved — what sits under each tower, which floor holds machines, what the sales sheet leaves out. Nobody reads them for you. We do.

What that turns up — from other projects’ filings:

ATS Knightsbridge · Sector 124, Noida

You pay for 10,000 sq ft. The floor inside your home is 6,982 sq ft. The rest is walls, shared circulation and services. Get both numbers written into your agreement before you pay any booking amount.

Oberoi Elysian · Goregaon East, Mumbai

“The building is complete.” The tower has reached full height — true. The same filed certificate, same page: sanitary fittings 6% done. Ask for a possession date in writing.

Godrej Aristocrat · Sector 49, Gurugram

Paying extra for the top floor? The terrace drawing shows what sits on the slab above those flats: the overhead water tanks, the lift machine rooms and the roof machinery. Ask which flat sits under which.

Prestige Camden Gardens · Thanisandra, Bengaluru

The approved parking table asks for 12 visitor spaces. It shows 0. Two-wheeler spaces: also 0. Ask in writing where visitors will park.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Raja Housing. View Raja Housing's full track record →
Raja Housing has 8 projects registered in Bangalore.

Other projects by this builder in Bangalore

Raja Platino
On track · 50% built · 3% sold
Raja Ritz Avenue - Phase II
No filings

Other RERA-registered projects in Mahadevapura

Major developers building in Mahadevapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Raja Ritz Avenue - Phase 1?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 10 Sep 2026