Developer RERA record
Embassy has 19 RERA-registered projects: 11 projects under construction, Bengaluru averaging 54% construction; 7 projects past their declared completion date. All figures are the developer's own regulator filings.
Under construction
Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.
| Project | City | Progress / possession |
|---|---|---|
| EMBASSY PARADISO | Bengaluru | 95% |
| EMBASSY VERDE | Bengaluru | 20% |
| EMBASSY GREENSHORE | Bengaluru | 10% |
| EMBASSY VERDE PHASE 2 | Bengaluru | 3% |
| Embassy Citadel | Mumbai | possession by Jun 2034 |
| Embassy One Thane | Mumbai | possession by Jun 2029 |
| Embassy Serenity - Phase 1 | Mumbai | possession by Jun 2030 |
| Embassy Terazza | Mumbai | possession by Dec 2031 |
| Marquis Residences Phase 1 | Mumbai | possession by Dec 2027 |
| Marquis Residences Phase 2 | Mumbai | possession by Dec 2028 |
| THE Embassy | Pune | possession by Jun 2030 |
Considering a specific Embassy project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
| Project | City | Status |
|---|---|---|
| Serene Amara by Columbia Pacific | Bengaluru | 100% built |
The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.
| Project | City | Declared date |
|---|---|---|
| Embassy Springs - Phase 2A, Apartments (72.0% built) | Bengaluru | 2023-02 |
| Embassy One (77.0% built) | Bengaluru | 2019-06 |
| Embassy Boulevard | Bengaluru | 2019-06 |
| Embassy Lake Terraces | Bengaluru | 2019-06 |
| Embassy Grove | Bengaluru | 2019-06 |
| Embassy | Nagpur | 2021-12 |
| Embassy One Thane - 1A 1B 1C | Mumbai | 2026-08 |
RERA complaints & orders
29 total complaints filed — more complaints than 81% of builders we track.
Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.
Buying in Embassy?
This is Embassy's overall RERA record — but you buy ONE flat, and the real risk is project-specific. The full report is the buy/wait call on your exact Embassy project: delivery risk, the sanctioned-plan detail (which side/tower to favour), land title, and what to verify before you pay.
This page is the free RERA filing summary. For Embassy, one reading of it goes further. Which flat should I ask for? — what the approved drawings and filed papers say about the flats, the parking, the approvals, and what to get in writing before you sign. That is the Project Review. See a real one first:
Project Review sample: Prestige Park Grove → · Project Deep Dive sample: Prestige Park Grove → · browse all sample reports →
Project Review · ₹4,999
A concise buying decision: unit choices, trade-offs and questions for the builder · 1 working day
Not useful to your decision? Full refund — no questions asked.
Project Deep Dive · ₹14,999
Detailed investigation of the drawings and documents, with evidence behind the buying decision · Prepared for your project
Not useful to your decision? Full refund — no questions asked.
Every report is about ONE project — open your Embassy project from the list on this page and buy it there, so the report you get is built from that project’s own filings.
Paying from outside India? Email hello@quietlist.in and we’ll send a payment link.
Stay ahead of the market
Get email alerts whenever we update our developer delivery indices, or when a pre-screened property from this builder becomes available.
No spam, ever. Unsubscribe any time.
Figures are Embassy's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.